HomeMy WebLinkAbout99-03986
i
WILLIAM J. LUMADUE, IN THE COURT OF COMMON PLEAS OF
Plaintiff CUMBERLAND COUNTY, PENNSYLVANIA
V. NO. 99- 3??GL2?
TIMOTHY HAKE, CIVIL ACTION - LAW
Defendant JURY TRIAL DEMANDED
NOTICE
You have been sued in court. If you wish to defend against the
claims set forth in the following pages, you must take action
within twenty (20) days after this Complaint and Notice are
served, by entering a written appearance personally or by
attorney and filing in writing with a court your defenses or
objections to the claims set forth against you. You are warned
that if you fail to do so the case may proceed without you and a
judgment may be entered against you by the court without further
notice for any money claimed in the Complaint or for any other
claim or relief requested by the Plaintiff. You may lose money
or property or other rights important to you.
YOU SHOULD TAKE THIS PAPER TO YOUR LAWYER AT ONCE. IF YOU
DO NOT HAVE A LAWYER OR CANNOT AFFORD ONE, GO TO OR TELEPHONE
THE OFFICE SET FORTH BELOW TO FIND OUT WHERE YOU CAN GET LEGAL
HELP.
Cumberland County Bar Association
2 Liberty Avenue
Carlisle, Pennsylvania 17013
(717) 249-3166
SNELBAKER, BRENNEMAN & SPARE, P. C.
By:
Attorneys for Plaintiff
LAW OFFICES
SNELBAKER.
BRENNEMAN
& SPARE
WILLIAM J. LUMADUE,
Plaintiff
V.
TIMOTHY HAKE,
Defendant
IN THE COURT OF COMMON PLEAS OF
CUMBERLAND COUNTY, PENNSYLVANIA
NO. 99- 39 FGA %.c+..-
CIVIL ACTION - LAW
JURY TRIAL DEMANDED
COMPLAINT
Plaintiff William J. Lumadue by his attorneys, Snelbaker,
Brenneman & Spare, P. C., submits this Complaint against
Defendant Timothy Hake and in support thereof, states the
following:
1. Plaintiff William J. Lumadue is an adult individual
residing at 146 Millers Gap Road, Enola, Cumberland county,
Pennsylvania.
2. Defendant Timothy Hake is an adult individual residing
at 6035 Wertzville Road, Enola, Cumberland County, Pennsylvania.
3. On or about October 19, 1998, Plaintiff and Defendant
entered into an agreement whereby Defendant agreed to construct
and erect within thirty days of commencing construction a metal-
sided garage and storage structure (the "structure") on property
located at 6990 Wertzville Road, Enola.
4. Pursuant to the terms of the parties, agreement entered
LAW OFFICES
SNELSAKER.
BRENNEMAN
a SPARE
into on or about October 19, 1998, Plaintiff agreed to pay
Defendant the cost of all materials and advance monies
periodically to Defendant for such materials to erect the
structure in an amount not to exceed $30,000.00, and in addition
thereto, pay Defendant the sum of $1,750.00 representing the
agreed charge for Defendant's labor in erecting the structure.
5. Attached hereto and incorporated by reference herein as
"Exhibit All is a copy of a proposal prepared by Defendant and
presented to Plaintiff, which proposal accurately memorializes
the terms of the parties' agreement, with the exception of the
additional terms as set forth in Paragraph 4, above.
6. On or about November 14, 1998, Plaintiff paid Defendant
the sum of $14,000.00 on account of materials to be purchased
for construction, at which time Defendant commenced construction
of the structure.
7. After Defendant commenced construction of the
structure, Plaintiff paid Defendant for certain materials
purchased by Defendant for use in erecting the structure and
authorized Defendant to utilize Plaintiff's VISA charge card to
purchase such materials.
8. After Defendant commenced construction of the
structure, Defendant improperly and without authority or
knowledge of Plaintiff purchased an impulse nailer with related
accessories at a price of $451.50 by use of Plaintiff's VISA
charge card.
9. In December, 1998, Plaintiff paid Defendant in advance
on account of Defendant's labor the sum of $1,500.00 due to
Defendant's insistence and representation that he was
desperately in need of money.
LAW OFFICES
SNELBAKER, _ z
BRENNEMAN
& SPARE
10. After Defendant commenced construction of the
structure, Plaintiff on numerous occasions requested Defendant
to work on and complete construction, which Defendant failed and
refused to do.
11. Defendant's last day of purported work in erecting the
structure was March 3, 1999, at which time the structure was not
even one-half completed.
12. Defendant materially breached his agreement with
Plaintiff of October 19, 1998 in the following particulars:
(a) by failing to complete construction of the
structure and furnish all labor for the
construction thereof;
(b) by failing to complete construction of the
structure within thirty days of November 14,
1998;
(c) by failing to complete all work in a workmanlike
manner; and
(d) by making a purchase by use of Plaintiff's VISA
charge account of an item not constituting a
material purchase for erection of the structure.
13. As a direct, factual and proximate result of the
breach by Defendant of the agreement as more fully set forth in
Paragraph 12, above, Plaintiff has been caused to sustain the
following losses and/or has expended the following sums:
(a) materials and labor to complete
construction of the structure: $10,684.79
(b) spouting: 382.50
LFW OFFICCS
SNELBAKER.
BRENNEMAN
& SPARE
(c) prepayment of compensation to
Defendant for labor: 1,500.00
-3-
(d) impulse nailer and accessories: 451.50
(e) Front door flashing:
Total:
151.00
$13,169.79
WHEREFORE, Plaintiff demands judgment against Defendant in
the amount of $13,169.79 together with interest and costs of
this action.
SNELBAKER, BRENNEMAN & SPARE, P. C.
By:
Keith 0. Brenneman, Esquire
44 West Main Street
Mechanicsburg, PA 17055
(717) 697-8528
Attorneys for Plaintiff
William J. Lumadue
Date: June 29, 1999
"W OFFICES
SNELBAKER.
BRENNEMAN
-4-
& SPARE
VERIFICATION
i verify that the statements made in the foregoing Complaint
are true and correct. I understand that false statements herein
are made subject to the penalties of 18 Pa. C.S. §4904 relating
to unsworn falsification to authorities.
William J. Lumadue
Date: June 29, 1999
LAW OFFICES
SNELBAKER.
BRENNEMAN
& SPARE
... 1,r
FROM:
PROPOSAL SUBMITTED T0:
we. +z v, ? ??. RL4
t?olD.. pA 1`?c.»S
PHONE
. ?a 1.n
PAGE NO. / . OF 'PAOE9
DATE /D „ / 1 - K-
JOB NAME
ADDRESS
CITY/STATE/LP
payment to be nied for
All material is guaranteed to he as speed. All work to be completed in a workmanlike manner according to standard practices Any alteration
or deviation from above specifications involving extra costs will be executed only upon written orders, and will become an extra charge over
and above the estimate All agreements contingent upon strikes, accidents, or delays beyond our control. T ' . propo b to acceptance
within days and is void thereafter at the option of the undersigned. Z `
Authorized Signature -
The
The above prices, specifications and conditions are hereby accepted. You are authorized to do the work as specified. Payments will be made
as outlined above.
ACCEPTED:
Signattim
Date
F F Z CONTRACTORS FORMS FORM NO EZ In
EXHIBIT A
f .. We hereby propose to furnish labor and materials - combl! " aecotdance vvfth"the above snedBratlnna ' ' irk er
0 1^
v/J
1v/
1
ay
l\
W
V
4•I
i
I
y
?
?
y
'I
?y
Wm w u
x w a
'1 ro
41
otRA pro 4
a a
?
?u xa
H a ?
D U
O ?
U
-
0
4
E
o+a H
?
: M Yy
p
o
i
SHERIFF'S RETURN - REGULAR
CASE NO: 1999-03986 P
COMMONWEALTH OF PENNSYLVANIA:
COUNTY OF CUMBERLAND
LUMADUE WILLIAM J
VS.
HAKE TIMOTHY
BRIAN BARRICK , Sheriff or Deputy Sheriff of
CUMBERLAND County, Pennsylvania, who being duly sworn according
to law, says, the within NOTICE AND COMPLAINT was served
upon HAKE TIMOTHY the
defendant, at 19:01 HOURS, on the 1st day of July
1999 at 6035 WERTZVILLE ROAD
ENOLA, PA 17025 CUMBERLAND
County, Pennsylvania, by handing to JEAN HAKE (WIFE)
a true and attested copy of the NOTICE AND COMPLAINT
and at the same time directing Her attention to the contents thereof.
Sheriff's Costs: So answers:
Docketing 18.00
Service 8.06
Affidavit .00
Surcharge 8.00
$J4$$ A-lrom? i e, e i
. Ub SN LLBA
by KER, BREE./N?NEMAN &SPARE
I
$r
I / I r epu y S eSworn and subscribed to before me
this 1 nu-A- day of?
777777
19 c-^ A. D.
?""$i nonocary
KENNETH F. LEWIS, ESQUIRE
Attorney I.D. 169383
1101 North Front Street
Harrisburg, PA 17102
(717) 234-3136
Attorney for Defendant
WILLIAM J. LUMADUE,
Plaintiff
V.
TIMOTHY HAKE,
Defendant
IN THE COURT OF COMMON PLEAS OF
CUMBERLAND COUNTY, PENNSYLVANIA
NO. 99 - 3986 CIVIL
JURY TRIAL DEMANDED
NOTICE TO PLEAD
TO THE PLAINTIFF NAMED HEREIN:
You are hereby notified to file a written response to the
enclosed Counterclaim within twenty (20) days from service hereof
or a judgment may be entered against you.
DATED: J f 51 l /lk;n4yG
KE ETH'F. LEWIS, ESQUIRE
KENNETH F. LEWIS, ESQUIRE
Attorney I.D. #69383
1101 North Front Street
Harrisburg, PA 17102
(717) 234-3136
Attorney for Defendant
WILLIAM J. LUMADUE, IN THE COURT OF COMMON PLEAS OF
Plaintiff CUMBERLAND COUNTY, PENNSYLVANIA
V. NO. 99 - 3986 CIVIL
TIMOTHY HAKE,
Defendant JURY TRIAL DEMANDED
ANSWER AND COUNTERCLAIM
Comes now, Defendant Timothy Hake, by his attorney,
Kenneth F. Lewis, who files this Answer and Counterclaim, averring
as follows:
ANSWER
1. Admitted.
2. Admitted.
3. Denied. Defendant offered a proposal to Plaintiff on
October 19, 1998. The proposal was never accepted. Plaintiff and
Defendant reached a different non-written agreement on or about
November 14, 1998 for the subject construction project.
4. Denied. Plaintiff agreed to pay Defendant $31,750.00
for the project. It is denied that Defendant was only to receive
$1,750.00 for his labor. No separate agreement was made separating
the costs of materials from the costs of labor. Plaintiff paid
$14,000.00 to Defendant at the time of the agreement to get the
project started. Plaintiff later made more payments to Defendant
and also permitted Defendant to use Plaintiff's credit card to make
purchases.
5. It is denied that the document attached to
Plaintiff's Complaint accurately memorializes the terms of the
parties' agreement. In addition to the facts set forth in
paragraph 04 above, the 30 day time frame was never made a part of
the agreement. Moreover, Plaintiff notified Defendant that the
construction would not be needed until June of 1999.
6. Admitted, except that the $14,000.00 paid was not
specifically delineated for construction materials only.
7. Admitted.
S. Denied. Plaintiff permitted Defendant to use his
credit card, indicating that he would be entitled to benefits from
the credit card company if charges were made on the card as opposed
to payments to Defendant by check or cash. Defendant used
Plaintiff's credit card account on at least three occasions.
Plaintiff did not specify the items that Defendant was permitted to
purchase.
9. It is admitted only that Plaintiff paid Defendant the
$1,500.00. The rest of paragraph 9 of Plaintiff's Complaint is
denied. To the contrary, Plaintiff wanted Defendant to accompany
him on a fishing trip to Florida. When Defendant balked because he
wanted to finish the project and because of a shortage of funds, it
was Plaintiff who offered the $1,500.00 payment and who assured
Defendant the project was in no rush to be completed so Defendant
could make the trip with him.
10. Denied. Defendant never refused to do work on the
project. See paragraphs 5 and 9 above regarding the time frame for
the project. It is admitted that Plaintiff called Defendant on two
or three occasions and questioned why full-time work was not being
performed on the dates of the telephone calls. Defendant explained
to Plaintiff that bad weather was preventing the continuing work on
those dates.
11. It is admitted that Defendantfs last day of work was
in the beginning of March. The rest of paragraph 11 is denied. To
the contrary, the structure was approximately 758-808 complete.
Moreover, Plaintiff prevented Defendant from continuing work on the
project when, without notification to Defendant, he put the garage
doors on the structure and locked Defendant out. Defendant learned
of Plaintiff fIs actions when he arrived at the project to continue
his work.
12. This paragraph is a conclusion of law to which no
response is required. To the extent a response is deemed to be
required, it is denied that Defendant breached the agreement. To
the contrary it was Plaintiff that breached the agreement.
(a) Denied. See paragraph 11 above;
(b) Denied. see paragraphs 5 and 9 above. Moreover, it
was Plaintiff who further held up the project due to his indecision
regarding the placement of the electrical system.
(c) Denied. As Plaintiff's Complaint fails to
specifically state what items to which this subparagraph refers,
Defendant cannot respond specifically to the generalized
allegation; and
(d) Denied. See paragraphs 6 and 8 above.
13. It is denied that Defendant breached the agreement
and that Defendant caused any damages whatsoever to Plaintiff.
Nonetheless, Defendant is without sufficient knowledge, information
and/or belief with regard to the sums claimed to be expended by
Plaintiff in the subparagraphs of paragraph 13. Strict proof is
demanded of same.
WHEREFORE, Defendant requests that Plaintiff fIs Complaint
be dismissed.
COUNTERCLAIM
I -- BREACH OF CONTRACT
14. Defendant incorporates paragraphs 1 through 13 above
as set fully forth herein.
15. The original contract price of $31,750.00 was
changed when work done by Defendant was destroyed by a wind storm.
Plaintiff informed Defendant that he received a $7,000.00 payment
from his insurance company for the rebuilding of the damage. The
parties agreed the original contract price would be increased due
to the extra work.
16. Defendant has expended $29,018.39 in costs on the
subject project.
17. Defendant anticipated a profit margin of $8,000.00
on the contract as he was going to do most of the work himself
(given Plaintiff's assurances that he had until June to finish the
project).
is. To date, Plaintiff has only paid Defendant
$23,508.00. This sum includes monies to Defendant for his labor,
to Defendant for the payment of subcontractors, and for materials
(as well as the $451.50 for the purchase of an impulse nailer and
accessories for Defendant which Defendant purchased using
Plaintiff's credit card).
19. Plaintiff has breached the subject agreement by
refusing to make payments to Defendant for continuing costs
associated with the project and by preventing Defendant from
completing his work as described above.
WHEREFORE, Defendant demands judgment in the amount of
$13,510.39 (representing out-of-pocket expenses and lost income),
for Court costs and for any other relief this Court deems just.
ZT - UNLAWFUL RETENTION OF PROPERTY
20. Defendant incorporates paragraphs 1 through 19 above
as set fully forth herein.
21. When Plaintiff locked Defendant out of the subject
job site, he also refused to return Plaintiff's tools, as well as
fishing equipment.
22. Though demand has been made, Plaintiff continues to
refuse to return the following items: extension ladder, heavy-duty
extension cord, orange 100 foot cord, 2 steel saw horses, transit,
tripod, transit pole, 2 fishing lures and 2 spools of fluorocarbon
leader material. These items have a total estimated value of
$974.00 (specific itemization to be supplied at trial).
, Defendant demands judgment against Plaintiff
in the amount of $974.00 or for the return of the aforementioned
items in the same condition as when they were left on Plaintiff's
property, for Court costs and for any other relief this Court deems
just.
DATED: 4144i
/ KENNETH F. LEWIS, ESQUIRE
Attorney I.D. #69383
1101 North Front Street
Harrisburg, PA 17102
(717) 234-3136
Attorney for Defendant
I hereby verify that the statements made in the foregoing
document are true and correct. I understand that false statements
herein are made subject to the penalties of is Pa.C.S. Section
4904, relating to unsworn falsification to authorities.
p !.,
Dated:
M HAKE
I hereby certify that I have served a true and correct copy of
the within Answer and Counterclaim to Plaintiff's counsel by
mailing same by U.S. Mail, postage prepaid at Harrisburg,
Pennsylvania addressed to:
Keith O. Brenneman, Esq.
44 West Main Street
Mechanicsburg, PA 17055
DATED: 511 ' % l t?
KE NETH F. LEWIS, ESQUIRE
F
l
?.
'
?.
I,
I
L 1
J I
LL
1
1. '
1.1
KENNETH F. LEWIS, ESQUIRE
Attorney I.D. x/69383
1101 North Front Street
Harrisburg, PA 17102
(717) 234-3136
Attorney for Defendant
WILLIAM J. LUMADUE,
Plaintiff
V.
TIMOTHY HAKE,
Defendant
TO: WILLIAM J. LUMADUE C/o
Keith O. Brenneman, Esq.
44 West Main Street
Mechanicsburg, PA 17055
IN THE COURT OF COMMON PLEAS OF
CUMBERLAND COUNTY, PENNSYLVANIA
NO. 99 - 3986 CIVIL
JURY TRIAL DEMANDED
YOU ARE IN DEFAULT BECAUSE YOU HAVE FAILED TO RESPOND TO
DEFENDANT'S ANSWER & COUNTERCLAIM IN THIS CASE. UNLESS YOU ACT
WITHIN TEN DAYS FROM THE DATE OF THIS NOTICE, A JUDGMENT MAY BE
ENTERED AGAINST YOU WITHOUT A HEARING AND YOU MAY LOSE PROPERTY OR
OTHER IMPORTANT RIGHTS. YOU SHOULD TAKE THIS NOTICE TO A LAWYER AT
ONCE. IF YOU DO NOT HAVE A LAWYER OR CANNOT AFFORD ONE, GO TO OR
TELEPHONE THE OFFICE SET FORTH BELOW TO FIND OUT WHERE YOU CAN GET
LEGAL HELP.
CUMBERLAND COUNTY BAR ASSOCIATION
2 LIBERTY AVENUE
CARLISLE, PA 17013
(717) 249-3166
1-800-990-9108
DATED: August 27, 1999
raL?
KEN •TH F. LEWIS, ESQ.
I hereby certify that I have served a true and correct copy of
the within Important Notice upon attorney for Plaintiff by mailing
same by U.S. Mail, postage prepaid at Harrisburg, Pennsylvania
addressed to:
Keith 0. Brenneman, Esq.
44 West Main Street
Mechanicsburg, PA 17055
4- 1 41!1q,
KENN H F. LEWIS, ESQUIRE
Dated: August 27, 1999
??
}
.
?_. ?•
C
`
?
?j !`?
(
?
` ?
r _.,
_
i- - J
?
- ? ?
L P? `??
\., s7
`' ,'? : ?;
.i '
Cj
WILLIAM J. LUMADUE, IN THE COURT OF COMMON PLEAS OF
Plaintiff CUMBERLAND COUNTY, PENNSYLVANIA
V. NO. 99-3986
TIMOTHY HAKE, CIVIL ACTION - LAW
Defendant JURY TRIAL DEMANDED
REPLY TO COUNTERCLAIM
Plaintiff William J. Lumadue by his attorneys, Snelbaker,
Brenneman & Spare, P. C., submits this Reply to Defendant's
Counterclaim as follows:
14. Plaintiff incorporates the averments set forth in
Paragraphs 1 through 14, inclusive, of Plaintiff's Complaint in
response to Paragraph 14 of Defendant's Counterclaim. By way of
further response, Paragraph 14 of Defendant's Counterclaim
should be stricken as improperly requiring a response to an
answer, a pleading to which no response is required as a matter
of law.
15. Admitted in part; denied in part. It is admitted that
the original contract price between the parties was $31,750.00.
It is specifically denied that the contract price was changed in
any manner when a portion of the work completed by the Defendant
was destroyed by a wind storm. It is further denied that
Plaintiff informed Defendant that Plaintiff received a $7,000.00
payment from an insurance company for purposes of rebuilding the
"W OFFICES wind storm damage. Further, it is specifically denied that the
SNELBAKER•
B& SPAREN Parties agreed that the original contract price would be
increased due to any work done by Defendant. To the contrary,
there was no such modification or change in the terms of the
parties' agreement as alleged by the Defendant.
16. Denied. It is denied that Defendant has expended
$29,018.39 in costs on the subject project. Strict proof of
such allegation is demanded of Defendant at the time of trial.
17. Denied. It is denied that Defendant anticipated a
profit margin of $8,000.00 on the contract since he was going to
do most of the work himself. On the contrary, it was
specifically agreed by the parties that Defendant's "profit"
would be his payment for labor in the amount of $1,750.00 as
averred in the Complaint. By way of further response, at no
time did Defendant agree to or undertake to do "most of the work
himself". To the contrary, Defendant used a substantial number
of subcontractors on the project and failed or refused to pay
his subcontractors. It is denied that Plaintiff gave any
assurance to Defendant that he had until June, 1999 in which to
finish work on the project.
18. Denied. It is denied that Plaintiff has only paid
Defendant $23,508.00. To the contrary, Plaintiff has paid
$29,594.50 to Defendant or on account of items purchased by
Defendant, and Defendant's labor.
19. Denied. Paragraph 19 sets forth an unwarranted
IAW OFFICES
SNELBAKER.
BRENNEMAN
& SPARE
conclusion of law to which no response is required by Plaintiff
-2-
pursuant to Pa.R.C.P. 1029(d). To the extent a response is
deemed necessary, it is denied that Plaintiff at any time
breached the parties' agreement by refusing to make payments to
Defendant for continuing costs associated with the project
thereby preventing Defendant from completing his work as that
work has been improperly characterized by Defendant in his
Counterclaim. To the contrary, Defendant breached the parties'
agreement as more fully set forth in Plaintiff's Complaint, the
averments of which are incorporated by reference herein.
WHEREFORE, Plaintiff requests this Court to dismiss Count I
of Defendant's Counterclaim with prejudice and enter judgment in
favor of Plaintiff in accordance with the demands set forth in
Plaintiff's Complaint.
20. The averments of Paragraphs 1 through 13 of
Plaintiff's Complaint and 14 through 19, inclusive, of this
Reply are incorporated by reference in this paragraph in their
entirety. By way of further response, Paragraph 20 of
Defendant's Counterclaim should be stricken as improperly
requiring a reply to an answer.
21. Denied. It is denied that Plaintiff locked Defendant
out of the subject job site and accordingly refused to return
Defendant's tools as well as fishing equipment. To the
contrary, Defendant abandoned any work on the project at a time
WW OFFICES when the structure was not substantially complete and at which I: ..
SNELBAKER,
BRENNEMAN
& SPARE 11 -3-
time Defendant continued to have free and open access to the
structure and therefore his tools.
22. Denied. It is denied that Plaintiff continues to
refuse to return the items listed in Paragraph 22 of Defendant's
Counterclaim. By way of further response, Plaintiff has been
put on notice by others that a number of the items set forth in
Paragraph 22 of Defendant's Counterclaim which Defendant
purports belong to him, are owned by other persons.
The value as alleged by Defendant for the items set forth
in Paragraph 22 of his Counterclaim is denied and strict proof
thereof demanded at time of trial.
WHEREFORE, Plaintiff requests this Court to dismiss Count
II of Defendant's Counterclaim with prejudice and enter judgment
in favor of Plaintiff in accordance with the demands made in
Plaintiff's Complaint.
SNELBAKER, BRENNEMAN & SPARE, P. C.
By:
Keith 0. Brenneman, Esquire
44 W. Main Street
Mechanicsburg, PA 17055
(717) 697-8528
Attorneys for Plaintiff
Date: September 3, 1999 William J. Lumadue
LAW OFFICES
SNELBAKER,
BRENNEMAN
6 SPARE -4-
VERIFICATION
I verify that the statements made in the foregoing Reply to
laim are true and correct. I understand that false
herein are made subject to the penalties of 18 Pa.
.S. §4904 relating to unsworn falsification to authorities.
J. Lumadue
Date: September 3, 1999
uw OFMCE6
SNELBAKCR.
BRENNEMAN
& SPARE
CERTIFICATE OF SERVICE
I, KEITH O. BRENNEMAN, ESQUIRE, hereby certify that I have,
on the below date, caused a true and correct copy of the
foregoing Reply to Counterclaim to be served upon the person and
in the manner indicated below:
FIRST CLASS MAIL POSTAGE PREPAID ADDRESSED AS FOLLOWS:
Kenneth F. Lewis
1101 North Front Street
Harrisburg, PA 17102
Wf4
Keith O. Brenneman, Esquire
SNELBAKER, BRENNEMAN & SPARE, P. C.
44 West Main Street
P. O. Box 318
Mechanicsburg, PA 17055
(717) 697-8528
Attorneys for Plaintiff
William J. Lumadue
Date: September 3, 1999
LAW OFFICES
SNELBAKER,
BRENNEMAN
& SPARE
PI
L.
ul
1, -7
I
'
V
t
. C.. .lj
1: _
C, on