HomeMy WebLinkAbout96-00110
.'
. i
,
i
'I
;
i
/
,
, I
f'
I :
i
, ,
,
.
~
Jl
~ I
11
Uj
~I
'~,
"
f
f~
J
,
,
,
I
I
oj
==1
-.91
I
o-i
j
.~
0'
z,
I ,<"),
n ' '
"
.....~
~.. . '
"
J 11 I- f
1 ~~
!
- CD <
I ..... 1 . r-i
0 tJ. M
015 .0' 0
J r-i p..~ I
~ ':l lfl
~ tl :g ~!:3 Ih~
<IJ <
Ul b~ 00
..... tJ ~
tJ Ul\O ...~
t <IJ .....
r-i 8,r-i ~ ~ .
r-i ~z
~ ~~ ",Ul~[~lfl
0 ~~
r-i 'C r 1J~~
7 r~
\0 c !~j~~
'" 0 ~!'l
tJ
.... a~ 0
l- t! < iil....~r-i .
.... .........
.
"
ii
"
-,
j!
I
l
I
',. In
i
- -.
lU~ <.., , :~
I ,- I
f::': : -. .<:, .
.
~/ ... - i
r.', ('.1 ;,)
" , I
(;: I , .
':!1
I .' :i~
,. :
I , ~., J
'. " I d
,
.. ,
CCI CONSTRUCTION COMPANY,
Plaintiff
IN THE COURT OF COMMON PLEAS OF
CUMBERLAND COUNTY, PENNSYLVANIA
CIVIL ACTION - LAW
vs.
CUMBERLAND VALLEY SCHOOL
DISTRICT,
Defendant
96-110 CIVIL TERM
vs.
THE RAY GROUP, INC.,
Additional Defendant
JURY TRIAL DEMANDED
ANSWER OF CUMBERLAND VALLEY SCHOOL DISTRICT
AND NOW comes Answering Defendant, CUMBERLAND VALLEY SCHOOL
DISTRICT, (hereinafter called "District") by its Attorneys,
Snelbaker & Brenneman, P.c., and responds to Plaintiff's
Complaint (as amended) as follows:
1. Admitted.
2. It is admitted that CCI is a general contracting company
engaging in private construction projects. After reasonable
investigation, District is without knowledge or information
SUfficient to form a belief as to the allegation that CCI
performs public construction projects in Pennsylvania and other
states; therefore, said averment is deemed to be denied pursuant
to Pa. R.C.P. 1029(c) and proof thereof is demanded at the trial
of the case.
LAw O"ICU
SNELPAKER
a
BRENNEMAN
J. District admits its identity but denies that it is
responsible to Plaintiff as a defendant or otherwise.
4. Admitted.
5. It is admitted that The Ray Group, Inc. was engaged by
. ,
the School District to be the architect for the Project pursuant
to the terms and provisions of a contract between the School
District and The Ray Group. As such, it is denied that The Ray
Group acted as and/or was an agent of the School District for the
project and it is averred, on the contrary, that the relationship
between the School District and The Ray Group is set forth and
specified in the agreement between said parties and any and all
averments to the contrary are specifically denied and strict
proof thereof is demanded. The remaining averments in Paragraph'
5 are conclusions of law to which no responsive pleading is
required and, therefore, said averments are deemed to be denied
pursuant to Pa. R.C.P. 1029(d) and strict proof thereof is
demanded.
6. All of the averments in the first sentence of paragraph
6 are admitted.
It is denied that the scope of work is
described in Part 1.OJ of Section 01010 of Project
Specifications. On the contrary, said Part and Section refer to
"Description of Contracts", not the scope of work for each
contract; the scope of work is not described. It is averred, on
the contrary, that the scope of work for each of the five (5)
contracts was and is set forth and stated in the various contract
LAw O'flCEII
SNELDAKER
It
BRENNEMAN
documents including, but not limited to, the contracts with each
prime contractor, the specifications and drawings for the
project, the General and SUpplemental Conditions of the
construction contracts, addenda, etc. and any and all documents,
drawings, records, etc. incorporated by reference in said
-2-
. ,
contract documents. The remaining averments in Paragraph 6 are
conclusions of law to which no responsive pleading is required
and, therefore, said averments are deemed to be denied pursuant
to Pa. R.C.P. 1029(d) and strict proof thereof is demanded.
7. After reasonable investigation, the District is without
knowledge or information SUfficient to form a belief as to the
truth of those averments contained in this paragraph with regard
to the basis for the bid of CCI and, therefore, said averments
are deemed to be denied pursuant to Pa. R.C.P. 1029(c) and strict
proof thereof is demanded at the trial of the case. The
remaining averments in this paragraph are conclusions of law to
which no responsive pleading is required and, therefore, the same
are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
8. Admitted.
9. Admitted.
10. Admitted.
11. Admitted.
12. Admitted.
IJ. Denied in part and admitted in part.
After reasonable
LAW a"ICElI
SNELDAKER
a
aRENNEMAN
investigation, the District is without knowledge or information
SUfficient to form a belief as to the truth of those averments
contained in this paragraph with regard to whether any such
sequence was intended by or permitted CCI to close-in Building
Section A before winter and, therefore, said averments are deemed
to be denied pursuant to Pa. R.c. P. 1029(c) and strict proof
thereof is demanded at the trial of the case. It is admitted
-J-
.
that CCI submitted a planned sequence of construction as stated
but it is averred that CCI subsequently submitted a revised
planned sequence of construction which was acceptable to CCI and
which would have permitted CCI to proceed in the same or similar
manner with regard to any close-in of a building section. The
remaining averments in this paragraph are conclusions of law to
which no responsive pleading is required and, therefore, the same
are deemed to be denied pursuant to Pa. R.C.P. 1029(d).
14. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 above, and
LAw O"ICU
SNELBAKER
a
eRENNEMAN
said response and averments are incorporated by reference herein.
The substance of any notification with regard to these items
speaks for itself and any and all averments to the contrary are
specifically denied and strict proof thereof is demanded. The
remaining averments in this paragraph are conclusions of law to
which no responsive pleading is required and, therefore, the same
are deemed to be denied pursuant to Pa. R.C.P. 1029(d).
15. Denied as stated. The substance of any notification
with regard to the matters set forth in Paragraph 15 speaks for
itself and any and all averments to the contrary are specifically
denied and strict proof thereof is demanded.
16. Denied as stated. The substance of any notification
speaks for itself and any and all averments to the contrary are
specifically denied and strict proof thereof is demanded. Those
averments contained in Paragraph 16 with regard to the scope of
work of the Sitework Contractor are conclusions of law to which
-4-
. ,
no responsive pleading is required and, therefore, said averments
are deemed to be denied pursuant to Pa. R.C.P. 1029(d) and strict
proof thereof is demanded. Furthermore, District incorporates by
reference herein the averments contained in its answer to
Paragraph 6 above, and realleges said averments to this Paragraph
16 as if the same were completely set forth here and at length.
17. It is averred, on the contrary, that CCI had, at all
times material hereto, access to the site and had access to all
or part of the building pad as of July 14, 199J so as to permit
and/or facilitate the commencement of work by and/or the
operations of CCI at the site and at that time and any and all
averments to the contrary are specifically denied and strict
proof thereof is demanded. It is specifically denied that CCI's
operations were in any way delayed and, in any event, all such
averments as well as the remaining averments in Paragraph 17 are
conclusions of law to which no responsive pleading is required
and, therefore, said averments are deemed to be denied pursuant
to Pa. R.C.P. 1029(d) and strict proof thereof is demanded.
18. District incorporates by reference herein those
averments contained in its answer to Paragraph 17 above and
real leges said averments to this paragraph as if the same were
LAW OP'"CU
SNELBAKER
a
BRENNEMAN
completely set forth herein at length. Further, after reasonable
investigation, the District is without knowledge or information
sufficient to form a belief as to the truth of the allegations
with regard to the schedule and/or any scheduling conflicts of
subcontractors of CCI and, therefore, said averments are deemed
-5-
LAW a'''CEII
SNELDAI<ER
a
BRENNEMAN
. ,
to be denied pursuant to pa R.C.P. 1029(c) and strict proof
thereof is demanded at the trial of the case. The remaining
averments of Paragraph 18 are conclusions of law to which no
responsive pleading is required and, therefore, said averments
are deemed to be denied pursuant to Pa. R.C.P. 1029(d) and strict
proof thereof is demanded. In any event, it is specifically
denied that District and/or any of its representatives caused the
disruption of CCI's schectule with its subcontractors and it is
averred, on the contrary, that the obligation to coordinate the
work and to maintain job progress was the responsibility of CCI
under the terms and provisions of the contract documents and that
any delay and/or disruption was caused, in whole or in part, by
the erroneous and unrealistic plan or schedule of CCI which was
made without CCI's coordination and cooperation with or
consideration of the other prime contractors on the project.
19. District incorporates by reference herein the averments
contained in its answers to Paragraphs 17 and 18 above and
realleges said averments in response to Paragraph 19 as if the
same were completely set forth herein at length. Furthermore, it
is averred that CCI is barred from any monetary compensation by
reason of the terms and provisions of the contract documents
including, but not limited to, the Supplemental Condition section
8.J.J of the General conditions of the contract for Construction.
The remaining averments in this paragraph are conclusions of law
to which no responsive pleading is required and, therefore, the
same are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
-6-
LAW O"ICtII
SNELBAI<ER
a
BRENNEMAN
. .
20. It is averred, on the contrary, that as part of
discussions and considerations between and among the prime
contractors on the project including CCI, it was agreed by such
prime contractors, including CCI, to modify and/or change the
sequence of construction so as to proceed with and perform such
construction in an orderly and workmanlike manner and any and all
averments to the contrary are specifically denied and strict
proof thereof is demanded.
21. After reasonable investigation, District is without
knowledge or information sufficient to form a belief as to the
truth of the alleged factual averments contained in Paragraph 21
with regard to the method and manner of work decided upon by CCI
and/or with regard to any alleged disruption of CCI's operations
and/or productivity and/or the alleged incurrence by CCI of
additional unanticipated costs and, therefore, said averments are
deemed to be denied pursuant to Pa. R.C.P. 1029(c) and strict
proof thereof is demanded at the trial of the case. Furthermore,
District incorporates by reference herein the averments contained
in its answers to Paragraphs 16 through 18 above and real leges
said averments to this paragraph as if the same were completely
set forth herein at length. The remaining averments in this
paragraph are conclusions of law to which no responsive pleading
is required and, therefore, the same are deemed to be denied
pursuant to Pa. R.C. P. 1029(d).
22. After reasonable investigation, District is without
knowledge or information sufficient to form a belief as to the
-7-
.
. ,
truth of the alleged factual averments contained in
Paragraph 22
with regard to alleged non-specific building line dimensional
problems and/or interior partition dimension problems and/or
those allegations with regard to the resolution of such alleged
dimensional problems, all such averments being too general and
non-specific to formulate a specific response, and, therefore,
said averments are deemed to be denied pursuant to Pa. R.C.P.
1029(c) and strict proof thereof is demanded at the trial of the
case. The remaining averments in this paragraph are conclusions
of law to which no responsive pleading is required and,
therefore, the same are deemed to be denied pursuant to Pa. R.C.
P. 1029(d).
2J. After reasonable investigation, District is without
knowledge or information sufficient to form a belief as to the
truth of the alleged factual averments contained in this
Paragraph 2J with regard to those matters which allegedly
adversely impacted on CCI's ability to perform its work, and,
therefore, said averments are deemed to be denied pursuant to Pa.
R.C.P. 1029(c) and strict proof thereof is demanded at the trial
of the case. Further, District incorporates by reference herein
the averments contained in its answer to Paragraph 22 above and
realleges said averments in response to Paragraph 2J as if the
same were completed set forth herein and at length. The
LAW O"ICES
SNELDAtcER
a
BRENNEMAN
remaining averments in this paragraph are conclusions of law to
which no responsive pleading is required and, therefore, the same
are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
-8-
.
24. It is denied that The Ray Group was an agent of District
as set forth ~nd stated in the answer to Paragraph 5 hereinabove,
LAw o,."cu
SNELBAtcER
a
BRENNEMAN
and said response and averments are incorporated herein by
reference thereto. After reasonable investigation, District is
without knowledge or information sufficient to form a belief as
to the truth of the alleged factual averments contained in
Paragraph 24 with regard to the nature and extent of any alleged
delay sustained by or on behalf of CCI and, therefore, said
averments are deemed to be denied pursuant to Pa. R.C.P. 1029(c)
and strict proof thereof is demanded at the trial of the case.
It is further averred, on the contrary, that proper, appropriate
and timely responses were provided on behalf of District to CCI
and/or to CCI's representative and that CCI and/or its
representatives could have and should have proceeded with its
operations and/or activities in connection with the project while
awaiting receipt of any and all such responses and the failure of
CCI and/or its representatives to proceed in such a manner was
the cause of or a contributing factor to any such alleged delay.
The remaining averments in this paragraph are conclusions of law
to which no responsive pleading is required and, therefore, the
same are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
25. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. It is averred, on the contrary, that CCI was
provided with appropriate and timely responses to any and all
-9-
LAW a,.,.lcr:.
SNELDAI<ER
a
BRENNEMAN
. ,
questions regarding the metal deck procurement and steel joist
procurement and any and all averments to the contrary are
specifically denied and strict proof thereof is demanded. Also,
District incorporates by reference herein the averments contained
in its answer to Paragraph 24 above and real leges said averments
to this paragraph as if the same were completely set forth here
and at length. The remaining averments in this paragraph are
conclusions of law to which no responsive pleading is required
and, therefore, the same are deemed to be denied pursuant to Pa.
R.C. P. 1029(d).
26. The alleged factual averments contained in Paragraph 26
are denied and it is averred, on the contrary, that at all times
material, CCI had access to the site and that none of the items
alleged made the performance of the work of CCI any more
difficult and/or less efficient or more costly and any and all
avermenta to the contrary are specifically denied and strict
proof thereof is demanded. District also incorporates by
reference herein those averments contained in its answers to
Paragraphs 16 through 18 above and realleges said averments to
this Paragraph 26 as if the same were completely set forth herein
at length. The remaining averments in this paragraph are
conclusions of law to which no responsive pleading is required
and, therefore, the same are deemed to be denied pursuant to Pa.
R.C. P. 1029(d).
27. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
-10-
LAW OPPle.:.
SNELDAtcEA
a
BRENNEMAN
. ,
and said response and averments are incorporated herein by
reference thereto. After reasonable investigation, District is
without knowledge or information sufficient to form a belief as
to the truth of the alleged factual averments contained in
Paragraph 27 as to the anticipations of CCI and, therefore, said
averments are deemed to be denied pursuant to Pa. R.C.P. 1029(c)
and strict proof thereof is demanded at the trial of the case.
Furthermore, District incorporates by reference herein the
averments contained in the answers to Paragraphs 16 through 18
above and realleges said averments to this paragraph as if the
same were completely set forth herein at length. The remaining
averments in this paragraph are conclusions of law to which no
responsive pleading is required and, therefore, the same are
deemed to be denied pursuant to Pa. R.C. P. 1029(d).
28. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. The remaining alleged factual averments in
Paragraph 28 are denied. It is averred, on the contrary, that
proper, appropriate and timely responses to any and all requests
of CCI were made and any and all averments to the contrary are
specifically denied and strict proof thereof is demanded. The
remaining averments in this paragraph are conclusions of law to
which no responsive pleading is required and, therefore, the same
are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
29. The alleged factual averments contained in Paragraph 29
-11-
LAW O"ICE6
SNELDAtcER
lit
BRENNEMAN
.
. '
are denied, and it is averred, on the contrary, that the weather
conditions for the time period in question neither commenced as
of the time noted nor would CCI's description as being
extraordinary and/or abnormal be appropriate, and all such
averments are denied and strict proof thereof is demanded.
Furthermore, at no time did District fail or refuse to provide
access to the site and it is averred, on the contrary, that CCI
had, at all times material, access to the site by way of a paved
road which continued to within a short distance of the site and
any and all averments to the contrary are specifically denied and
strict proof thereof is demanded. The remaining averments in
this paragraph are conclusions of law to which no responsive
pleading is required and, therefore, the same are deemed to be
denied pursuant to Pa. R.C. P. 1029(d).
JO. Denied. It is averred, on the contrary, that it was not
and is not the responsibility of District to address winter
conditions since this was the responsibility of CCI under the
terms and provisions of the contract documents and any and all
averments to the contrary are specifically denied and strict
proof thereof is demanded. The remaining averments in this
paragraph are conclusions of law to which no responsive pleading
is required and, therefore, the same are deemed to be denied
pursuant to Pa. R.C. P. 1029(d).
Jl. The alleged factual averments contained in Paragraph J1
are specifically denied. It is averred on the contrary that the
contents of the Job Conference Meeting Minutes respond to CCI's
-12-
allegations. Furthermore, the nature and extent of the progress
of the project at the time in question was the result of the
conduct of CCI and any and all averments to the contrary are
specifically denied and strict proof thereof is demanded. The
remaining averments in this paragraph are conclusions of law to
which no responsive pleading is required and, therefore, the same
are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
J2. The alleged factual averments contained in Paragraph J2
are specifically denied. Each and everyone of the matters
alleged in said Paragraph J2 came within and were the
responsibility of CCI as set forth and provided in the contract
documents for the project and any and all averments to the
contrary are specifically denied and strict proof thereof is
demanded. The remaining averments in this paragraph are
conclusions of law to which no responsive pleading is required
and, therefore, the same are deemed to be denied pursuant to Pa.
LAW O'PlCF.1S
SNELBAKER
/lr
BRENNEMAN
R.C. P. 1029(d).
JJ. After reasonable investigation, District is without
knowledge or information sufficient to form a belief as to the
truth of the alleged factual averments contained in Paragraph JJ
with regard to alleged attempts, deployment and/or extra work on
the part of CCI and, therefore, said averments are deemed to be
denied pursuant to Pa. R.C.P. 1029(c) and strict proof thereof is
demanded at the trial of the case. The remaining averments in
this paragraph are conclusions of law to which no responsive
pleading is required and, therefore, the same are deemed to be
-lJ-
. ,
denied pursuant to Pa. R.C. P. 1029(d). In any event, it is
averred by way of further response that those items referenced in
Paragraph JJ came within and were the responsibility of CCI
pursuant to the terms and provisions of the various contract
documents.
J4. The content of Paragraph J4 consists of a series of
conclusions of law to which no response is required; therefore,
the same is deemed to be denied pursuant to Pa. R.C.P. 1029(d).
If said content is determined to be an averment of factual
material, all is denied. On the contrary, for all the reasons
set forth in Paragraphs 29 through J2, sUDra, the responsibility
for the matters complained of were entirely accepted by CCI by
reason of the Contract.
J5. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. After reasonable investigation, District is
without knowledge or information sufficient to form a belief as
to the truth of the alleged factual averments contained in
Paragraph J5 with regard to allegations of disruption and/or the
sustaining of additional costs and loss of time and, therefore,
said averments are deemed to be denied pursuant to Pa. R.C.P.
1029(c) and strict proof thereof is demanded at the trial of the
LAW o'fleu
SNE:LBAKER
a
BRENNEMAN
case.
The remaining averments in this paragraph are conclusions
of law to which no responsive pleading is required and,
therefore, the same are deemed to be denied pursuant to Pa. R.C.
-14-
. ,
P. 1029(d). Furthermore, it is averred that the responsibility
for coordination of the prime contractors on the project was that
of CCI and/or the other prime contractors as set forth and
provided in the contract documents including, but not limited to,
those referenced in answer to Paragraph 6 above.
J6. It is admitted that the quotation from the Contract is
accurate, but is a conclusion of law to which no response is
required; therefore, the application of such quotation to the
case at hand is deemed to be denied pursuant to Pa. R.C.P.
1029(d).
LAW o,,,cu
SNELBAI<EA
a
BRENNEMAN
J7. It is admitted that CCI performed the matters averred in
part but the nature and extent of same were inadequate and
insufficient and, therefore, not in compliance with the terms and
provisions of the contract documents with regard to the
responsibility of CCI to provide coordination. The remaining
av.rm.,..... in this paragraph are conclusions of law to which no
r.spondivo ploading is required and, therefore, the same are
d..med to U~ doniod pursuant to Pa. R.C. P. 1029(d).
J8. It is averred that the project specifications referenced
in Paragraph 38 speak for themselves and any and all averments to
the contrary are specifically denied and strict proof thereof is
demanded. Also, CCI's responsibility for coordination is set
forth and stated in the contract documents and is referenced in
such documents and not limited to the section noted in the
Complaint, and it is specifically denied that CCI performed the
coordination required by the terms and provisions of the contract
-15-
"'i~..~.. _"." 1
documents and any and all averments to the contrary are
specifically denied and strict proof thereof is demanded. The
remaining averments in this paragraph are conclusions of law to
which no responsive pleading is required and, therefore, the same
are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
J9. It is averred that the terms and provisions of the
project specifications and/or other contract documents speak for
themselves and any and all averments to the contrary are
specifically denied and strict proof thereof is demanded. The
averments contained in Paragraph J9 are, in any event,
conclusions of law on the part of CCI to which no responsive
pleading is required and, therefore, said averments are deemed to
be denied pursuant to Pa. R.C.P. 1029(d) and strict proof thereof
is demanded. In addition, reference should be made to other
contract documents and records including the contracts between
and among the parties which clearly establish that any such
coordination was and is the responsibility of CCI and not the
responsibility of District and/or The Ray Group.
40. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. It is admitted that CCI made various
LAW a"leu
SNELBAtcER
BI
BRENNEMAN
allegations with regard to the other prime contractors on the
project and all such allegations were investigated, discussed,
and considered including similar allegations made against CCI.
Both District and The Ray Group responded to and took the
-16-
LAw a'flCU
SNELBAKER
a
S"INNEMAN
appropriate and timely action as required by the contract
documents for the project with regard to each and every matter
referenced and any and all averments to the contrary are
specifically denied and strict proof thereof is demanded. The
remaining averments in this paragraph are conclusions of law to
which no responsive pleading is required and, therefore, the same
are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
a. It is denied that CCI had "sidewalk work" in
the courtyard. On the contrary, CCI was required to
install only two small stoops at exterior doors. It is
denied that any "problems" were caused by access
through two J'O" doors.
b. It is denied that the Plumbing contractor was
required to perform "slab work" and that the Electrical
contractor was required to perform "duct work".
c. After reasonable investigation, District is
without knowledge or information sufficient to form a
belief as to the truth of the averment that the alleged
delay of light fixtures had a "serious impact on CCI's
schedule"; therefore, the same is deemed to be denied
pursuant to Pa. R.C.P. 1029(c) and proof thereof is
demanded at the trial of the case.
d. After reasonable investigation, District is
without knowledge or information sufficient to form a
belief as to the truth of the averments in paragraph
40(d); therefore, the same are denied pursuant to Pa.
-17-
LAw a,,.ICElI
SNELBAtcER
a
BRENNEMAN
R.C.P. 1029(c) and proof thereof is demanded at the
trial of the case.
It is denied that District failed and/or refused to coordinate as
alleged. On the contrary, it is averred that CCI was the author
of its grievances for failure and/or refusal to coordinate and
cooperate with other contractors, District and architect.
41. It is denied that District set any schedules which were
unrealistic. The only schedule issued by District occurred on or
about October 4, 1994, after CCI was granted a 60-day
construction time extension and after CCI had alienated itself
with other contractors by its lack of cooperation and
coordination. After reasonable investigation, District is
without knowledge or information sufficient to form a belief as
to the truth of the alleged factual averments contained in this
paragraph with regard to alleged acceleration of work, disruption
of the progress of work, and/or incurrence of additional costs
and, therefore, said averments are deemed to be denied pursuant
to Pa. R.C. P. 1029(c) and strict proof thereof is demanded at
the trial of the case. The remaining averments in this paragraph
are conclusions of law to which no responsive pleading is
required and, therefore, the same are deemed to be denied
pursuant to Pa. R.C. P. 1029(d).
42. It is denied that CCI was required to perform the
alleged extra slab work because of the fault of anyone other than
CCI. On the contrary, the alleged "extra" work was required as a
correction because of CCI's own disturbance of the earth under
-18-
LAW O"'''ICU
SNELBAI<ER
llO
BRENNEMAN
the concrete slab. The remaining averments in this paragraph are
conclusions of law to which no r~sponsive pleading is required
and, therefore, the same are deemed to be denied pursuant to Pa.
R.C. P. 1029(d).
4J. The existence of "Exhibit C" is admitted; however, it is
de~ied that District had any contractual or other obligation to
represent acceptability of the site to CCI. The remaining
averments in this paragraph are conclusions of law to which no
responsive pleading is required and, therefore, the same are
deemed to be denied pursuant to Pa. R.C. P. 1029(d).
44. Admitted generally; however, it is denied that the area
in question was not properly compacted prior to CCI's disturbance
thereof.
45. Admitted.
46. It is admitted that CCI corrected the slab caused by
settlement. It is denied that CCI was not at fault. On the
contrary, it is averred that the cause of the settlement was
CCI's disturbance of the subject earth without proper compaction.
The remaining averments in this paragraph are conclusions of law
to which no responsive pleading is required and, therefore, the
same are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
47. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. It is denied that CCI was backcharged
improperly for the alleged materials. On the contrary and
-19-
LAw a""CIE8
SNELBAKER
a
BRENNEMAN
pursuant to the response in Paragraphs 48 and 49, infra, the
materials were to be provided by CCI pursuant to the Contract.
The remaining averments in this paragraph are conclusions of law
to which no responsive pleading is required and, therefore, the
same are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
48. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. The factual averments in Paragraph 48 are
admitted. By way of further response it is averred that CCI
agreed to provide 2517-C sinks which include faucets and
bubblers. The remaining averments in this paragraph are
conclusions of law to which no responsive pleading is required
and, therefore, the same are deemed to be denied pursuant to Pa.
R.C. P. 1029(d).
49. The factual averments in Paragraph 49 are denied. On
the contrary, CCI specifically agreed to provide sinks of the
2517-C type which are defined to include the faucets and bubblers
accessories. The reference to "C" identifies the sinks to
include the accessories. The remaining averments in this
paragraph are conclusions of law to which no responsive pleading
is required and, therefore, the same are deemed to be denied
pursuant to Pa. R.C. P. 1029(d).
50. The factual averments in Paragraph 50 are denied. On
the contrary, the affirmative averments in Paragraphs 48 and 49,
sUDra, are incorporated herein by reference thereto as the true
-20-
LAw O,.,ICU
SNELBAI<EA
a
BRENNEMAN
facts. Therefore, it is further denied that District wrongfully
refused to pay again for sinks expressly agreed to be furnished
by CCI under the Contract. The remaining averments in this
paragraph are conclusions of law to which no responsive pleading
is required and, therefore, the same are deemed to be denied
pursuant to Pa. R.C. P. 1029(d).
51. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. It is admitted that the deductive change
order was issued by District. The remainder of the paragraph
contains only conclusions of law to which no response is
required; therefore, the same is deemed to be denied pursuant to
Pa. R.C.P. 1029(d). If such content is determined to be a
factual averment, it is denied. On the contrary, the affirmative
averments in Paragraphs 48, 49 and 50, sUDra, are incorporated
herein by reference thereto.
52. The content of Paragraph 52 is a conclusion of law to
which no response is required; therefore, it is deemed to be
denied pursuant to Pa. R.C.P. 1029(d).
5J. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. It is denied that CCI was directed to form
the concrete pads. It is admitted that District directed CCI to
reinforce and pour concrete in the forms pursuant to CCI's
-21-
LAW O,."Ct:1I
SNELIIAKER
a
BRENNEMAN
contract to provide reinforcing mesh, set anchor bolts and pour
concrete at the ticket booths in forms installed by anothsr
contractor. It is denied that such work was "extra". On the
contrary, the subject work was specifically within CCI's
contract. The remaining averments in this paragraph are
conclusions of law to which no responsivo ploading is required
and, therefore, the same are deemed to be denied pursuant to Pa.
R.C. P. 1029(d).
54. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. The remaining averments in Paragraph 54 are
denied. On the contrary, the subject work was included in CCI's
contract by reference to the construction plans at "SP2", "SP6"
and "SP2J" as the responsibility of CCI, and for which no
additional compensation is allowable. The remaining aVerments in
this paragraph are conclusions of law to which no responsive
pleading is required and, therefore, the same are deemed to be
denied pursuant to Pa. R.C. P. 1029(d).
55. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. After r~asonable investigation, District is
without knowledge or information sufficient to form a belief as
to the truth of the alleged factual averments contained in
Paragraph 55 with regard to CCI's alleged ability to perform its
-22-
LAW a"lcr:6
SNELBAKER
a
eRENNEMAN
, ,
work and/or any alleged adverse effect on the part of CCI and,
therefore, said averments are deemed to be denied pursuant to Pa.
R.C.P. 1029(C) and strict proof thereof is demanded at the trial
of the case. The remaining averments in this paragraph are
conclusions of law to which no responsive pleading is required
and, therefore, the same are deemed to be denied pursuant to Pa.
R.C. P. 1029(d).
56. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. After reasonable investigation, District is
without knowledge or information sufficient to form a belief as
to the truth of the alleged factual averments contained in
Paragraph 56 except to the extent of those admitted and/or denied
in the answers of District to Paragraphs 1 through 55 above, and,
therefore, said averments are deemed to be denied pursuant to Pa.
R.C.P. 1029(c) and strict proof thereof is demanded at the trial
of the case. Furthermore, it is specifically denied that this
was a critical path project and any and all averments to the
contrary are specifically denied and strict proof thereof is
demanded. Furthermore, after reasonable investigation, the
District is without knowledge or information sufficient to form a
belief as to the truth of those averments contained in Paragraph
56 as to the nature and extent of alleged damages and/or delays
sustained by CCI and, therefore, all such averments are deemed to
be denied pursuant to Pa. R.C.P. 1029(C) and strict proof thereof
-2J-
LAw O"'''ICr:.
SNELBAICER
a
BRENNIMAN
is demanded at the trial of the case. The romaining averments in
this paragraph are conclusions of law to which no responsive
pleading is required and, thereforo, tho Bame are deemed to be
denied pursuant to Pa. R.C. P. 1029(d).
57. It is denied that The Ray Group waD an agent of District
as set forth and stated in tho answor to Paragraph 5 hereinabove,
and said response and averments aro incorporated horein by
reference thereto. After reasonable investigation, District is
without knowledge or information sufficient to form a belief as
to the truth of the alleged factual averments contained in
Paragraph 57 with regard to what was anticipated by CCI and/or
with regard to the nature and extent of any alleged costs and/or
time and, therefore, said averments are deemed to be denied
pursuant to Pa. R.C.P. 1027(c), and strict proof thereof is
demanded at the trial of the case. The remaining averments in
this paragraph are conclUDions of law to which no responsive
pleading is required and, therefore, the same are deemed to be
denied pursuant to Pa. R.C. P. 1029(d).
58. It is denied that The Ray Group was an agent of District
as set forth and stated in the answer to Paragraph 5 hereinabove,
and said response and averments are incorporated herein by
reference thereto. After reasonable investigation, District is
without knowledge or information sufficient to form a belief as
to the truth of the allegod factual averments contained in
Paragraph 58 with regard to tho nature, extent and amount of
alleged damages sustainod by CCI and, therefore, said averments
-24-
, .
are deemed to be denied pursuant to Pa. R.C.P. 1029(c) and strict
proof the~eof is demanded at the trial of the case. The
remaining averments in this paragraph are conclusions of law to
which no responsive pleading is required and, therefore, the same
are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
59. After reasonable investigation, District is without
knowledge or information sufficient to form a belief as to the
truth of the alleged factual averments contained in Paragraph 59
with regard to what was anticipated by CCI and/or the alleged
amount of any extension of contract time and, therefore, said
averments are deemed to be denied pursuant to Pa. R.C.P. 1029(c)
and strict proof thereof is demanded at the trial of the case.
The remaining averments in this paragraph are conclusions of law
to which no responsive pleading is required and, therefore, the
same are deemed to be denied pursuant to Pa. R.C. P. 1029(d).
NEW HATTER
By way of further answer and defense, District avers the
following:
60. The term "Contract Documents" as used hereinbelow
includes all General Construction contractual documents between
LAw O"ICU
SNELBAKER
a
BRENNEMAN
District and CCI including, but not limited to, the Agreement,
Plans, Drawings, Specifications, General Conditions of the
Contract for Construction, Supplementary Conditions, being too
voluminous to be attached hereto but are in the possession of
CCI. Said contract Documents are incorporated herein by
reference thereto.
-25-
" ' .
61. The Contract Documents between the parties herein
contain certain "General Conditions of the Contract for
Construction" which include the following specific provision in
Supplementary Conditions Section 8.J.J of Article 8, page
00800-5 :
"No payment or compensation or claim for damages shall
be made to the Contractor as compensation for damages
for any delays or hindrances from any cause whatsoever
in the progress of the Work, notwithstanding whether
such delays be avoidable or unavoidable. The
Contractor's sole remedy for delays shall be an
EXTENSION OF TIME ONLY, pursuant to and only in
accordance with this Paragraph 8.J, such extension to
be a period equivalent to the time lost, by reason of
any and all of the aforesaid causes, as determined by
the Architect. In consideration for this grant of a
time extension, the Owner and the Architect shall not
be held responsible for any loss or damage or increased
costs sustained by the Contractor through any delays
caused by the Owner or Architect or any other
contractor or on account of the aforesaid causes or any
other cause of delay. In the event the Contractor
shall choose to litigate this clause or issue and loses
said litigation, the Contractor shall reimburse the
Owner and the Architect for their reasonable attorney'S
and expert witness fees and all other costs and
expenses incurred by them in the litigation."
62. CCI is the "Contractor" and District is the "Owner" as
those ter~s are used in Section 8.J.J quoted in Paragraph 61
hereinabove.
LAW o,."etll
SNELBAtcER
a
BRENNEMAN
6J. CCI is barred from any monetary compensation by reason
of Contract Documents between the parties hereto including, but
not limited to, Section 8.J.J quoted in Paragraph 61 hereinabove.
64. The Complaint of CCI against District fails to state a
cause of action against District upon which relief may be
granted.
65. CCI was engaged by District to perform work and/or
-26-
.. .
services in connection with the construction project in question
and such work and/or services were set forth and stated in the
Contract Documents between the parties and/or any and all
Contract Documents and all such work and/or services were to be
performed in conformance with the terms and provisions of said
Contract Documents and in a careful and workmanlike manner and
consistent with recognized and accepted standards, practices
and/or procedures in the construction industry.
66. The work performed and/or to be performed by or on
behalf of CCI on the construction project in question was not
performed in a careful and workmanlike manner nor was all such
work performed in accordance with the terms and provisions of the
Contract Documents nor in accordance with recognized and accepted
standards, practices and/or procedures in the construction
industry and, therefore, District is not liable to CCI.
67. The alleged claims and/or cause(s) of action alleged by
CCI were caused, in whole or in part, by the breach(es) of the
Contract Documents between the parties by CCI and such breach(es)
preclude CCI from any recovery against District, said claims and
any and all liability on the part of District being specifically
denied in the first instance and, therefore, District is not
liable to CCI.
LAw O'''CtI
SNEL8AtcER
1II
BRENNEMAN
68. Any alleged liability of District with regard to the
Complaint of CCI, said liability being specifically denied in the
first instance, is limited by the terms and provisions of the
Contract Documents and, therefore, District is not liable to CCI.
-27-
LAW O"ICU
SNELBAKEn
a
BRENNEMAN
, .. .
.. . .
69. The alleged claims and/or cause(s) of action made by
CCI in its complaint, said alleged claims and/or cause(s) of
action being specifically denied in the first instance, are
barred by the doctrines of waiver, estoppel and/or laches and,
therefore, District is not liable to CCI.
70. CCI has failed to mitigate its alleged claims and/or
damages, said alleged claims and/or damages and any liability on
the part of District being specifically denied in the first
instance, and CCI engaged in careless and negligent conduct which
aggravated any such alleged claims and/or damages and, therefore,
District is not liable to CCI.
71. The responsibility for coordination of the work of the
prime contractors on the Construction Project was vested in CCI
as set forth and provided in the Contract Documents.
72. CCI failed and neglected to perform the coordination of
work among the prime contractors as required by the Contract
Documents.
WHEREFORE, District respectfully requests your Honorable
Court to dismiss Plaintiff CCI's Complaint and enter judgment in
favor of Defendant District and against CCI.
COUNTERCLAIM
District avers the following claims and cause of action
against CCI:
7J. The averments contained in Paragraphs 60 through 6J
hereinabove are realleged herein and incorporated herein by
reference thereto as though set forth in full in separate
-28-
LAW a"lcu
SNELDAKER
a
BRENNEMAN
I I . .
" .
paragraphs.
74. By contesting, disputing and litigating the provisions
of section 8.J.J quoted above, CCI has breached and continues to
breach the terms thereof.
75. Because CCI contests, disputes and litigates the
provisions of said section 8.J.J, District has incurred and will
incur in the future substantial attorney fees and costs involved
in the defense of this matter.
76. Because of CCI's contest, dispute and litigation as
aforesaid, District may require the engagement of expert
witnesses and other defensive costs and expenses resulting in
substantial expense to the District.
77. The terms of said Section 8.J.J require CCI to
reimburse District for District's reasonable attorney's fees,
expert witness fees and all other costs and expenses incurred in
the litigation.
WHEREFORE, District requests your Honorable Court to enter
judgment in favor of Defendant District and against plaintiff CCI
in the amount of its reasonable attorney's fees, expert witness
fees and all other costs and expenses incurred and to be incurred
in this litigation.
N, P.C.
By
d c. Snelbaker
Attorney Registration Number 06J55
44 West Main Street
Mechanicsburg, PA 17055-0J18
(717) 697-8528
Attorneys for Defendant Cumberland
Valley School District
-29-
('-)
"
"
f:l In
~;:i !::: ~ ,n
... ... ... rs
~ ... c " i:l;J
..... 111 111
~~ ... 'tl 'tl ,-l ;!;
" " " ~8); Lll5 z
. ..... llJ llJ ~ ~ ~
"'Ill ~ 111 ,-l ... ... :;.;<;;:l ~3
~ffi r-i 8 llJ llJ Siid fa 3 ~
'" I'> I'>
~ El ~ ~~ ~ ~ ~ c
~'" . .-< ~~el ;j
0 . III . , 111 lXl8 ~ 5
8gj~ U Ul Ul U C H~ I1l ~ ~
:> l::i :> ~ 0 ~~ Z m
Z ..... ... E9UP I'>
1&0 I-< 0 ~ ... (..1-10 ~ 9 it ~ I,j 0
00',-l ..... . ... B~u ~ ..: .
t; !:i 'tl Lll a 0 p
~u z..... 'tl 1Il'tl ~~ t:; ~ '"'
g; S~ ~ 0 ..: I&o.....c ~ <~ '( rJ
8~t;U ~g ti 01'>111
III ~8 ~ 5< ~
":0 Z >< Lll
~~ ~ 7 0 ;,a 7- :t
u U
E91-< ~~ V1 '"
..... !Ol~ ~ ;;;
Z .....'" u
..... UO\ U Ul'>
-
. . . .
..
~
It .. '. :
,
Ia
, -,....-' .'
. ~-...,...,.----- --- - ....'2J '
- .......~ ... I ;31 . ""-.., .
. . ,.' .
. -
~
,
.
"
.'
It.
..
.
CCI CONSTRUCTION COMPANY, INC. IN THE COURT OF COMMON PLEAS
Plaintiff : CUMBERLAND COUNTY, PENNSYLVANIA
v.
CUMBERLAND VALLEY SCHOOL
DISTRICT
.
.
.
.
.
.
NO. C;~J-II ()
,. .
1996' T'~\I"
Defendant
COMPLAINT
1. Plaintiff is CCI Construction Company, Inc., a
corporation, which maintains a principal place of business at
4720 Old Gettysburg Road, Mechanicsburg, PA 17055 (hereinafter
"CCI").
2. CCI is a general construction contractinq company which
engages in the performance of pUblic and private construction
projects in Pennsylvania and other states.
J. Defendant is Cumberland Valley School District, a
school district governed by the laws of the Commonwealth of
Pennsylvania, which maintains a principal place of business at
6746 Carlisle Pike, Mechanicsburg, PA 17055 (hereinafter
"District").
4. In 199J, the District issued for pUblic bidding and
award a construction project then known as "New Middle School,
Cumberland Valley School District" (hereinafter "Project").
5. The architectural consultant for the Project, engaged
by the District, was The Ray Group, Inc., which maintains a
f , , ~
principal place of business at 4 South Fourth street, Lebanon, PA
17042 (hereinafter "The Ray Group"). At all times l'elevant
hereto, The Ray Group acted as the agent of the District for the
Project.
PROJECT BIDDING TO MULTIPLE PRIME CONTRACTORS
6. The Ray Group prepared the Projent'~ plans and
specifications for the District, and, at the instruction of the
District, issued requests for bid on the Project for competitive
pUblic bidding for five (5) separate prime contracts, to-wit:
General Construction; Hearing, Ventilation, Air-conditioning;
Plumbing; Electrical; sitework. The scope of work for each of
the five contracts is more clearly described in the Project
Specifications, section 01010, Part 1.0J Description of Contract.
A copy of Section 01010, Part 1.0J is attached hereto, marked
Exhibit "A", and incorporated herein by reference.
7. CCI submitted its competitive bid for the General
Construction contract based upon the plans and specifications
issued by the District. Following bidding, CCI was determined by
the District to be the lowest responsible bidder for the General
Construction contract.
8. On May 27, 199J, CCI was notified by The Ray Group, at
the direction of the District, that the District had passed a
resolution, stating its intent to award the prime contract for
General Construction to CCI.
2
"
,..
.
9. On June 16, 199J, CCI and the District entered into a
prime contract for the general construction of the New Middle
School Project. A true and correct copy of the Agreement portion
of the general construction contract documents is attached
hereto, marked Exhibit "B" and incorporated herein by reference.
The remaining contract documents are too voluminous to be
attached hereto, but are in the POssession of the District.
10. The District awarded the four (4) other prime contracts
on the Project to the following contractors:
HVAC Contract: Frey Lutz Corp. of Lancaster, PA
Plumbing Contract: Herre Bros. Inc. of Enola, PA
Electrical Contract: Warren Electrical Construction Corp.,
of Myersville, MD
Sitework Contract: Adams County Asphalt, Harrisburg, PA
11, Ray Group issued to CCI a Notice to Proceed on June 22,
199J.
eeI'8 CON8TRUCTION 8EOUENCE FOR BUILDING CON8TRUCTIOH
12. CCI's original schedule submitted to the District for
bUilding construction (which did not include sitework outside of
the building footprint) depicted a construction start date of
July 12, 199J (commencement of foundations) with a contract
completion date of August 15, 1994.
1J. CCI's original planned sequence of construction was to
construct Building Section A (classroom wing) first with a
transition to Building Section B (administration and aUditorium),
and thereafter to BUilding Section C (gymnasium and mechanical
,:
;1
I'
i
\
/
di
t !!
"
J
I I.
; I
-
,
. .
.
.
rooms). This sequence permitted CCI to close-in Building Section
A before the onset of winter weather.
14. On June 23, 199J, CCI notified the District's agent,
The Ray Group, of CCI's intent to mobilize foundation operations
during the week of July 12, 199J, with its intent to commence
foundation work on the east side of the two-story classroom wing,
facing the main entry and parking lot.
15. CCI also gave notice of its intent to mobilize the job
site office trailer during the week of July 12, 199J to prepare
for job site administration, provided that the front parking lot
stone base was completed by the sitework contractor.
16. CCI gave notice that CCI's actual building construction
on the site was contingent upon the District providing to CCI a
complete building pad and access to the pad, both of which work
items were within the prime sitework Contractor's scope of work.
17. The District did not give access to the site to CCI in
accordance with CCI's plan and schedule. CCI received access to
the building pad and confirmation from the District that the pad
was acceptable for construction on July 2J, 199J, facilitating a
July 26, 199J start. Accordingly, CCI's operations were delayed
by the District, and/or agents or other prime contractors of the
District.
18. The District's failure to provide access as planned
disrupted CCI's schedule of subcontractor operations and required
CCI to resolve scheduling conflicts among eCI's subcontractors,
and constituted interference with CCI's performance of its
4
,~
. .
"
.
~
contract work. This was the consequence of the District not
adhering to its obligation to maintain the job progress of the
prime sitework contractor. The timely performance of the
Sitework contractor's work, and the completion of the building
pads according to specification, were both critical to the start
dates of the downstream work activities within the scope of work
of the General Construction contract.
19. CCI is entitled to additional Contract time and
monetary compensation for the disruption caused by the District's
failure to maintain the required Project progress of other prime
contractors performing critical work.
THB DISTRICT'S IMPRUDENT RESEOUENCINO or CONSTRUCTIOH AHD
THB DBrECTIVE DES ION IN THE DISTRICT'S PLANS
20. On June 24, 199J, CCI was requested by the District's
Mechanical/Electrical Engineer to resequence CCI's logic for
construction of the buildings. CCI was requested to construct
Building Section C first in order to accommodate the mechanical,
electrical and plumbing prime contractor.
21. FUlfilling its contractual duty to cooperate, CCI re-
sequenced its work to commence work on Building Section C. The
District's prime Sitework Contractor was not completed with the
building pad for Building section C, and CCI was forced to begin
foundation excavation where it could be constructed in order to
avoid interference with the prime sitework Contractor. However,
the prime sitework Contractor's untimely performance of building
5
...
,,'
.~. , .
4
pad work disrupted CCI's sequence of operations and productivity
which caused CCI to incur additional unanticipated costs.
22. During the week of June 28, 199J, CCI discovered latent
design defects in the District's plans. The design for the
building was erroneous in that the specified building lines would
not close dimensionally and numerous interior partition
dimensions were also in error. These interior dimensional
problems were significant because the majority of partitions were
masonry walls extending to footings. The dimensional errors were
continuous and significant in number. The District, and/or its
agents or contractors, failed to resolve these dimensional errors
efficiently and promptly.
2J. The building line dimensional problems (both exterior
and interior) had the following significant adverse impact on
CCI's ability to perform its contract work as well as overall
Project progress:
(a) Development of structural steel shop drawings
could not be completed by CCI's subcontractor.
This prevented CCI's submission of shop drawings
to The Ray Group for approval and prevented CCI
from ordering the fabrication of steel as planned;
(b) The building dimensions needed to be re-surveyed,
recalculated, and re-staked by CCI on several
occasions;
(c) Underslab plumbing work by the prime Plumbing
Contractor was disrupted and delayed;
6
'- . ~
~
Cd) CCI was forced to perform footing/foundation work
out of planned sequence, and was disrupted and
delayed; and
ee) CCI's critical path activities were adversely
impacted.
24. The District, and/or its agent The Ray Group, failed to
provide responses to CCI's questions about dimensional defects in
the plans until August 5, 199J, which response was untimely.
This six (6) week delay rippled through the Project and delayed
the completion of the fabrication of steel until the end of
October 199J. This, in turn, yielded a delay of nine (9) weeks
from the original schedule for delivery of structural steel and
caused an unanticipated and unreasonable increase in Project
costs and time for completion.
25. CCI incurred a similar delay because of the District's,
and/or its agent The Ray Group's, failure to provide timely
responses to questions regarding metal deck procurement and steel
joist procurement. As a result, CCI suffered unanticipated and
unreasonable delay and increase in Project costs and time for
completion caused by the District's untimely Project
administration.
26. After CCI was given access to the site on July 26,
199J, areas of the building pad were not up to the lines and
grades called for in the plans, including but not limited to the
Dock Area, Mechanical Room Area, depressed slab area and the
AUditorium. CCI was, in fact, forced to perform work out of
7
. .
'.'
. ,
.
sequence, which made contract work more difficult, less efficient
and more costly.
27. The District, and/or its agent The Ray Group, was
ineffective in maintaining its prime site Contractor on an
established schedule and agreed upon sequence. The timely
performance of the prime Site Contractor's scope of work was
critical to the efficient performance of CCI's general
construction contract work. Therefore, the District's failures
caused CCI's performance to be out of planned sequence, less
efficient, and more costly. CCI did not anticipate in its bid or
in its schedule of its work that the District would administer
the prime site Contractor's contract so ineffectively. As a
consequence, CCI has suffered adverse cost and time impact of the
District's poor administration.
28. The District, and/or its agent The Ray Group, never
provided meaningful or timely responses to the design problems
recited in the foregoing paragraphs, and notwithstanding numerous
requests for schedule adjustments and effective Project
administration, the Project and CCI were forced by the District
to fall behind schedule.
IZTRBMI WINTZR CONDITIONS IN 1993-94
29. Extraordinary cold and abnormally snowy and icy weather
conditions occurred as early as November 199J and continued
throughout the winter of 199J-94. The District had the duty to
provide access to the site in order for CCI to perform its
B
,~
, ~'
.
building construction under the General Construction contract.
The District failed and refused to provide access to the New
Middle School Project site which sat approximately one-quarter
mile away from the nearest paved private access road and on top
of a steep hill, during the abnormally snowy, icy and cold
conditions described above. The District had resources to make
the building site accessible to prime contractors, but the
District failed and/or refused to do this.
JO. The District's failure to address the winter conditions
deprived CCI of access to the building site for construction
work, and made building construction progress effectively
impossible.
Jl. At the time of the onset of winter conditions, the
building itself was not enclosed as defined by the
specifications, that is, the building did not have a roofing
system in place, nor were exterior walls substantially complete,
nor was the mbtal deck complete. At Job Conference Meeting No.
16, January 20, 1995, The Ray Group agreed that Project success
was not benefitted by enclosing a partially completed building.
J2. Notwithstanding the above, CCI suffered from the
fOllowing unreasonable demands made by the District:
(a) to remove snow and ice from the building access
road. Snow and ice removal from the building
access road was not a part of CCI's contract
obligation under the scope of work for General
Construction contract;
9
.-
. ,
r
.
(b) to temporarily enclose the building, when the
building was not ready for temporary enclosure;
(c) to heat the unenclosed building;
(d) to work in hazardous working conditions; and
(e) to reschedule and resequence work inconsistent
with the Project schedule.
JJ. Using its own resources, CCI attempted, under protest,
to resolve the adverse impact of the extreme weather conditions
by deploying its own resources to achieve progress on the
Project, which include the extra work of snow and ice removal.
CCI made it clear that such extra work was to be compensated by
the District.
34. As a consequence of the foregoing, CCI incurred
additional costs which were not reasonably anticipated at the
time of bidding, for which CCI deserves compensation.
TaB DISTRICT'S .AILURE TO COORDINATE PRIM. CONTRACTORS
J5. The District, and its agent The Ray Group, failed and
refused to carry out contract responsibilities to coordinate the
work of the multiple prime contractors performing the Project.
This failure or refusal was unanticipated by CCI at the time CCI
submitted it bid, and caused CCI to be disrupted from its plan
and sequence of work and to suffer additional costs and loss of
time in CCI's effort to perform its General Construction contract
work.
10
~
.
J6. The General Conditions of Contract, Article 6,
Construction by Owner or by Separate Contractors, provides:
6.1.J - The Owner shall provide for coordination of the
activities of the Owner's own forces and of each
separate contractor with the Work of the Contractor,
who shall cooperate with them. The Contractor shall
participate with other separate contractors and the
Owner in reviewing their construction schedules when
directed to do so. The Contractor shall make any
revisions to the construction schedule and [deleted
words] deemed necessary after a joint review and mutual
agreement. The construction schedules shall then
constitute the schedules to be used by the Contractor,
separate contractors and the Owner until subsequently
revised.
J7. CCI regularly and in good faith attempted to coordinate
its contract progress with the District, The Ray Group, and with
other prime contractors (1) by compiling and inputting submitted
schedule information, (2) by reporting the status of the schedule
at each bi-weekly progress meeting, and (J) by corresponding with
all parties.
J8. CCI performed this coordination in furtherance of the
Project Specifications, at Section 01010, Part 1.07 which
provides for every contractor to be responsible for the
coordination of the progress of his work with the progress of
other contractor's work and provides that each contractor shall
perform his work at such time and in such manner as not to delay
or otherwise interfere with the work progress of other
contractors. The District, the Ray Group, and other prime
contractors failed and/or refused to coordinate in order to
maintain proper Project progress.
11
,
.
.
J9. The Project Specifications place coordination
responsibilities on The Ray Group, as the District's Architect
for progress meetings at Section 01200 - Project Meetings, as
follows:
1.0J ADMINISTERING MEETINGS
A. The Architect will schedule, administer, record and
report all meetings.
B. Reporting: No later than 7 days after each progress
meeting date, the Architect will distribute copies of
minutes of the meeting to each party present and to
other parties who should have been present.
1.05 PROGRESS MEETINGS
A. Progress meetings will be held every two weeks. Times,
dates and location shall be agreed upon by the
Architect, Owner and Contractor.
B. Attendance: Job superintendent, Prime Contractors,
Owner and Architect as appropriate to agenda topics for
each meeting. Major subcontractors and suppliers shall
attend when requested.
C. The first progress meeting shall be held soon after
start of work. All Contractors, having previously
carefully examined Drawings and Specifications, shall
present to The Architect any questions that have
arisen.
D. Agenda:
1. Review and correct or approve minutes of the
previous progress meeting.
2. Review other items of significance that could
affect progress.
J. Include topics for discussion as appropriate to
the current status of the Project.
4. Construction Schedule: Review progress since the
last meeting. Determine where each activity is in
relation to the Construction Schedule, whether on
time or ahead or behind schedule. Determine how
construction behind schedule will be expedited;
secure commitments from parties involved to do so.
Discuss whether schedule revisions are required to
ensure that current and subsequent activities
shall be completed within the Contract Time.
12
, .
.
5. Review the present and future needs of each entity
present, including such items as:
a. Interface requirements
b. Time
c. Sequences
d. Deliveries
e. Off-site fabrication problems
f. Access
g. site utilization
h. Temporary facilities and services
i. Hours of Work
j. Hazards and risks
k. Housekeeping
l. Quality and Work standards
m. Change Orders
n. Documentation of information for payment
requests
40. CCI notified the District, and, its agent The Ray
Group, of the repeated failures of other prime contractors to
coordinate with CCI, including the fOllowing particular areas:
(a) The Sitework contractor refused to perform his
grading work in the school courtyard. This
refusal prevented CCI from performing its sidewalk
work in the courtyeard, and created further
problems relating to limited access via two J' 0"
doors;
(b) The District did not provide timely access as
planned to the building pads to CCI during the
199J construction season, which caused disruptions
to the prime Plumbing contractor performing slab
work and the prime Electrical contractor
performing duct work;
(c) In the spring of 1994, the delivery of light
fixtures for installation by the electrical
13
, I
,
,
contractor was late, which had a serious impact on
CCI's schedule;
(d) In the fall of 1994, the site contractor, the
electrical contractor and the mechanical
contractor were not on schedule as agreed upon in
previous progress meetings, and they did not
provide scheduling information as required by
their contract.
,
ij
~
,
il
In all of the above, the District, and/or its agent, The Ray
Group, failed and/or refused to fulfill contractual obligations
to coordinate, all of which worked to the detriment of CCI.
41. The District insisted that CCI meet unrealistic
construction schedules, arising out of problems caused by the
District, The Ray Group, and other prime contractors, and caused
CCI to accelerate its work to meet the District's unilaterally
ordered milestones. This caused disruption to the progress of
CCI's contract work. CCI incurred additional costs to accelerate
its work to comply with the directives of the District, for which
compensation is due to CCI.
BITRA WORK TO CORRECT BUILDING SLAB SETTLEMENT
42. CCI was required by the District to perform extra work
to correct a building slab settlement which occurred as a result
of the improper actions or inactions of the District, The Ray
Group, and/or the District's Sitework prime contractor.
14
"
43. On July 15, 199J, before CCI accepted the building pad
for the ntart of building construction, the District (through its
Project Manager) acknowledged to CCI that the building pad met
all architect and engineer requirements and was acceptable for
the start of building construction. This was evidenced by the
signature of Project Manager Ed Haldeman in a document attached
hereto, dated July 14, 199J, marked Exhibit "C" and incorporated
herein by reference.
44. CCI had expressed its concern with the insufficiency of
evidence of compaction tests by the District for fill operations
undertaken by the District's prime sitework contractor, and had
informed the District of this concern prior to slab construction.
There was no conclusive evidence that the District had performed
compaction tests on every lift of backfill (one test per every
1600 square feet per fill layer) as specified in Project
specifications, section 02200.
45. The building slab-on-grade experienced settlement in
Building section B. The District required CCI to perform
remedial work to correct the settlement deficiency.
46. CCI corrected the slab settlement at substantial
expense for which compensation is due and owing. CCI was not at
fault in causing the above described settlement, which settlement
would not have occurred had the District's Sitework Contractor
adequately compacted and tested the building pad as requested by
CCI.
15
.'
IMPROP~R BACKCHAROE FOR SINK ACCESSORIES
47. The District, and/or its agent The Ray Group, has acted
improperly by back-charging CCI for procurement of materials
which were to be furnished and installed by the Plumbing
contractor, a separate prime contractor of the District.
48. The District, and/or its agent The Ray Group, directed
CCI to furnish sink type S-6 and S-7 from Elkay Catalog No. DRKR-
25l7-C. The District, and/or its agent The Ray Group, directed
CCI to provide this sink type complete H1th accessories known as
faucets and bubblers.
49. CCI's scope of work did DQt include the furnishing of
the accessories known as faucets and bubblers for sink type S-6
and S-7 by clear reference to the District's plans and
specifications. The Complete Sink Schedule on architectural
drawing A-35 provides two specific notes as follows:
"GC [general contractor] to furnish and install sinks
(& accessories on S-12 only)
"P.C. [plumbing contractor] to furnish and install
accessories (except S-12) II
50. The District's request for an S-6 or S-7 sink places no
obligation on CCI to provide accessories for that type of sink,
particularly where that obligation is squarely within the
Plumbing contractor's scope of work. When the District requested
CCI to furnish these accessories, CCI rightly insisted upon an
ADD change order to the CCI contract. The District wrongfully
refused.
16
51. Notwithstanding the above, the District, or its agent
The Ray Group, unilaterally issued a deductive change order to
CCI for the cost of furnishing and installing the referenced
faucets and bubblers, which deductive change order is
inconsistent with the terms of the plans and specifications.
52. The District deductive change order in the amount of
$2,711.15 is an improper change order which must be reversed.
IXTRA WORK TO ~URNISH AND INSTALL CONCRBTB PADS AT TICK IT
BOOTHS
5J. CCI was directed to form and place three concrete pads
at the ticket booths by the District and/or its agent The Ray
Group in August of 199J. This work was extra to CCI's scope of
work.
54. The directed work was part of an alternate bid item
(Alternate SDP-4) that was not part of the General Construction
bid package, and was in fact an bid alternate under the Sitework
contractors bid package. In as much as the District, or its
agent, The Ray Group, directed CCI to perform this work, this
work was performed under protest in order to expedite the Project
with the expectation that CCI would be compensated for the extra
work.
COMPBNSABLB IMPACTS AND EXTENSION OF CONTRACT TIMI
55. CCI's ability to perform its scope of contract work on
time and within its budget was severely and adversely affected by
the actions and omissions of the District, and/or its agent The
17
Ray Group, and/or other prime contractors of the District, all of
which is the responsibility of the District.
56. Contract perf~rmance was extended on the critical path
solely as a result of the following actions and omissions of the
District, and/or its agent The Ray Group, and/or other prime
contractors of the District:
(a)
(b)
(c)
District providing late site access;
incomplete building pad;
building pad not having been compacted according to
specification;
building pad compaction not having been tested
(d)
according to specification;
(e) The Ray Group's requirement that the sequence of work
not be as CCI planned, but instead be reversed to suit
the interests of the District;
(f) design errors;
(g) untimely resolution of design errors;
(h) untimely responses to shop drawing submissions and
other CCI requests for information;
(i) failure to coordinate the multiple prime contractors by
assuring adherence to CCI's Project progress schedule;
(j) failure to adhere to Project specifications in the
issuance of directions to prime contractors;
(k) failure to make payment for compensable extra work;
(I) wrongfully threatening CCI with liquidated damages;
18
(D) wrongfully creating a job climate which forced CCI's
acceleration of contract work and project schedule, and
forced CCI to incur costs in the field and in the home
office which were never reasonably anticipated, and
impacting CCI adversely;
(n) causing an unanticipated and unforeseeable Project
delay of approximately twenty (20) weeks, and
disruption to orderly Project completion.
57. All of the above actions and/or omissions were not
reasonably anticipated at the time CCI submitted its bid to
perform the General Construction contract work. CCI should not
have been made to incur extra costs nor extra time, caused by
these actions and/or omissions.
SUMMARY or DAMAGES
58. CCI suffered damages as a direct result of the
District's, or its agent The Ray Group's wrongful and erroneous
contract administration, contract interpretation and error or
omission, as follows:
A. GBNBRAL CONDITION ITEMS:
1.
superintendent 20 Weeks at $1419.00/wk.
Foreman 20 Weeks at $Jo.44/hr.
on-site Project Engineer -
Full time on-site for 6 months
due to magnitude of problems
General Labor 20 Weeks at $19.67/hr.
Trailer Rental 5 Months at $J08/mo.
= $ 28,380.00
2.
=
24,352.00
J.
=
24,160.00
15,7J6.00
1,540.00
4.
=
5.
=
19
E. DAMAGES RELATED TO OWNER'S ~AILURE
TO TEST COMPACTION OF SUBGRADE
Damages related to District's failure to test
compaction of subgrade resulting in removal
and replacement of concrete slabs
Labor
Material
Equipment
Testing
Total Dir~ct Costs
profit (10%)
Subtotal Direct Costs
$ 16,559.00
2,212.00
6,103.00
1. 598.00
$ 26,472.00
2.647.00
$ 29,119.00
F. DAMAGES RELATED TO IMPROPER BACICHARGE
Damages related to improper backcharge for
faucets and bubblers
Deduct Change Order Refused by CCI
Subtotal
$ 2,711.00
G. DAMAGES RELATED TO REJECTED CHANGE ORDER
Damages related to Owner's directive to
install ticket booth concrete pads
Total Direct Costs
Profit (10%)
Subtotal
$
$
1,J90.00
139.00
1,529.00
H. TOTALS
1. General Conditions - $12J,170.00
2. Extended Home Office Overhead 85,J16.00
J. Snow Removal 21,768.00
4. Additional survey 2,014.00
5. Damages Related to Owner's Failure to
Test Compaction of Subgrade 29,119.00
6. Damages Related to Improper Backcharge - 2,711.00
7. Damages Related to Rejected
Change Order 1.529.00
Total $265,627.00
21
,
59. CCI suffered from the performance of work beyond the
originally anticipated contract time, and CCI is entitled to an
extension of contract time in the amount of 140 calendar days.
WHEREFORE, CCI Construction co., Inc. demands jUdgment in its
favor and against Cumberland Valley school District in the sum of
$265,627.00 plus the granting of an extension of Contract Time of
140 calendar days, plus attorneys fees, as may be appropriate, and
such other relief as this Court deems appropriate.
POWELL, TRACHTHAN, LOGAN,
CARRLE & BOWMAN, P.C.
By () ,))It.<t~':fl eVh'tl-,..J
C. Grainger Bowman
I. D. #15706
David W. Francis
I.D. #5J718
Michael W. Winfield
I.D. #72680
114 North Second Street
Harrisburg, PA 17101
(717) 2J8-9JOO
Date: January 4, 1996
22
CUMBERLAND VALLEY MIDDLE SCHOOL 201.91
SECTION 01010 . SUMMARY OF WORK
PART I - GENERAL
1.01 RELATED DOCUMENT~
A, Drawings and general prOVisions of Contract, including General and
Supplementary Conditions and other Division-I Specification Sections,
apply to this Section.
1.02 PROJECT DESCRIPTION
A. The proposed project wlll be located in the eXisting Cumberland Valley
School District campus in Silver Spring TownShip, Cumberland County,
PennsYlvania, along U.S. Route II, Carli~le Pike. The eXisting site is
comprised of 102 acres of land,
B, The building 101111 be a "T" shaped structure with the two story Academic
wing located along the top of the tee and the one story auditorium,
Administration, Cafeteria, Gymnasium, Technologies, Music and Support
SerVice portion located on the base of the tee.
C. The building's construction is rated non-combustible, comprised of a steel
frame with non-load bearing masonry interior and exterior walls, The
primary exterior finished will be split-face CMU and brick, with aluminum
frame windows and tinted glaZing. The bUilding roof will be flat/slightly
pitched steel Joists, steel deck and rigid Insulation with an adhered
single membrane roof. The primary Interior finishes 101111 be painted CMU
and gypsum board partitions, acoustical tile ceilings or painted exposed
structure (at gym, shops, auditorium and cafeteria); the floors 101111 be
carpet, VCT, terrazzo, quarry tile, ceramic tile and wood (at gym and at
stage).
1.03 DESCRIPTION OF CONTRACTS
.
A. The oroiect Is soecif1ed to be multiole construction contracts
segregated into the fOllowing contracts, each requiring a separate
proposa 1 :
Contract No, 1 General ConstructioQ shall Include all labor, materials,
equipment and services necessary for the complete construction of all Work
shown on draWings and described In Division O. I, & 2 through 12 and 14 of
the Specifications, eXcluding sections indicated for Contracts 2. 3, 4 &
5, and including building foundation excavation and backfill In Section
02200.
Contract No. 2 "VAC Constructio'1 shall include all labor. materials,
equipment and services necessary for the complete construction of all work
shown on draWings and described In divisions O. 1 and 15 of the
specifications for HVAC work,
SUHHARY OF WORK
01010-1
CUMBERLAND VALLEY MIDDLE SCHOOL 201-91
Contrict No, 3 Plumbing Construction shill include ill libor, miteriils,
equipment and services necessary for the complete construction of all work
shown on drawings ind described In Divisions 0, I ind 15 of the
speciflcitlons for plumbing work.
Contract No.4 Electrical Construction shall include all libor, materials,
equipment and services necesnry for the complete construction of ill work
shown on drawings ind described In Divisions 0, I ind 16 of the
specifications for electrlcil work.
Contrict No,S Sltework Construction shall include ill labor, materials,
equipment, and services necessny for the complete construction of all
work shown on driwings ind described in Division 0, I, 2 & 13 of the
specificitions for sitework, excluding bUilding foundation excavation and
bickfill in Section 02200.
1.04 WORK PROVIDED BY OWNER
A. The Owner will provide loose finishing and equipment not specified
herein and references as Not in Contract (N.I.C.), or furnished by
Owner.
1.05 WORK SEOUENCE
A. This project has no phasing requirements.
1.06 CONTRACTOR USE OF PREMISES
A. General: during the construction period the Contractor shall have full eu
of the premises for construction operations, including use of the site.
B. Confine operations to areiS within Contract limits Indicated. Portions of
the building or site beyond areas in which construction operations are
indicated are not to be disturbed.
C. Contractor shall maintain means of egress from building as required by
code.
1.07 PROJECT COORDINATION
A. Every Contractor shall be responsible for the coordination of the progress
of their work with the progress of all other contractor's work.
B, Inumuch is Proiect comDletion within the time limit is dependent upon
cooperition of those engaged therein, it is imperative that each
Contractor perform his work at such time and in such a manner as not to
delay or otherwise interfere with work progress of other Contractors, If
any Contractor's work depends upon proper execution or results of another
Contractor's work, the former shall inspect the work and report any
defects therein to the Architect.
SUItlARY OF WORK
01010-2
.
CUMBERLAND VALLEY MIDDLE SCHOOL 201-91
00500 AGREEMENT BETWEEN OWNER AND CONTRA~
THIS AGREEMENT, entered into this 16th day of
.June 199.1. , by and between Cuwberla~d Va] ley
School District, Cumberland County, PA hereafter called the Owner', and
I an
individual, of
OR
cons 1st i ng of
, a partnersh i p,
and
as all the partners, having its principal office at
OR
CCI Construction
State of Pennsylvania
4720 Old GettysburQ Road.
having
MechanlcsburQ. Cumberland
, a Corporation of the
its principal office at
County, Pennsylvania,
hereinafter called the "Contractor" (and hereinafter treated as if of the
s1n9ular number and neuter gender) WITNESSETH, that the "Contractor" and the
"Owner", for the considerations named, agree as follows:
WHEREAS, the Owner heretofore has advert i sed for proposals I as
required by Pennsylvania laws, for the Genera Construction
work necessary for the construction 0
the Cumberland Valle Middle Schoo
, and has received proposals t erefor; an
WHEREAS, the Owner has considered the proposals so received and has
made an award to the Contractor based upon the proposal so received from the
Contractor.
NOW, therefore, in consideration of the mutual promises, covenants
and agreements herein contained, the Owner and Contractor promise, covenant and
agree, as follows:
1. SCOPE OF WORK - The "Contractor" shall furnish all of the materials
and perform all of the Genera 1 Constrll.ct 1 on
Work shown on the drawings and described In the specifications entitled
as prepare y T e Ray Group Inc., Arc itects & P anners, 127 E. Orange Street,
Lancaster, Pennsylvania 17602 (acting as and in these Contract Documents entitled
the "Architect" and shall do everything required by this Agreement and Contract
Documents.
AGREEMENT
00500.1
. .
CUMBERLAND VALLEY MIDDLE SCHOOL 201-91
2. TIME OF COMPLETION - The work to be performed under this contract
shall be CORmenced within ten (10) calendar days after notification by the
"Owner" or the "Architect" to start work and shall be completed within 420
calendar days. The "Contractor" shall be liable to the "Owner" for any damages
sustained by the latter through extra engineering, Architects' or other costs of
any nature Incurred by reason of the "Contractor's" failure to complete Its work
by the above date, or any extension thereof granted under Article 8.3 of the
"General Conditions".
3. PAYMENTS - The "Owner" shall pay the "Contractor" for the performance
of the General Co~tructlon Contract, subject to additions and
deductions provided therein, In current funds, the sum of
SEVEN MILLION. FIVE HUNDRED SIXTY-THREE THOUSAND. FIVE HUNDRED FORTY DOLLARS
(S7,55~.540 ) which sum represents the Contractor's base bid or adjust~d base
bid as a result of the acceptance of the following alternates by the Owner as
follows:
G-I - ~1O.460
Payments shall be made to the Contractor In accordance with Article 9 of the
"General Conditions."
4, CONTRACT DOCUMENTS shall consist of the following all of which are
part of the contract between the parties as though repeated herein or hereto
attached:
A. This Agreement
B. Performance and Payment Bond
C. General Conditions AlA A201
D Supplementary Conditions
E. Specifications
F. Drawings.
G. Addenda Identified as follows: Addendum II: 4/30/93:
Addendum #2: 5/6/93: Addendum #3: 5/6/93 (faxed):
Addendum #4: 5/12/93 (faxed).
AGREEMENT
00500-2
CUMBERLAND VALLEY MIDDLE SCHOOL 201,91
5. REPRESENTATIONS OF CONTRACTOR - The Contractor represents and warrants:
That it is financially solvent and experienced in and competent to
perform the work and to furnish the plant, materials, supplies or
equipment, to be so performed or furnished by it;
That it is familiar with all Federal, State, Municipal and
Departmental laws, ordinances and regulations, which may in any way
affect the work of those employed herein, including, but not limited
to, any special acts relating to the work or to the project of which
it is a part;
That such temporary and permanent work required by the Contract
Documents as is to be done by it can be satisfactorily constructed
and used for the purposes for which it is intended and that such
construction will not injure any person or damage any property;
and
That it has carefully examined the plans, specifications and site of
the work, and that it has satisfied itself as to the nature and
location of the work, the character, quality and quantity of surface
and sub-surface materials likely to be encountered, the character of
equipment and other facil ities needed for the performance of the
work, and the general and local conditions, and all other materials
which may in any way affect the work or its performance.
6, HEIRS, ETC. - This Agreement shall bind and inure to the benefit
of the heirs, legal representatives and successors and assigns of both parties
hereto, except that this sentence shall not be interpreted to grant any right of
assignment of any nature whatsoever to the Contractor.
D,
".
A.
B.
C.
7. The Owner and the Contractor each intend to be bound I ega lly by th i s
Agreement.
IN WITNESS WHEREOF, the parties have executed the Agreement the day and
year first above written.
BY:
At."~
JlAnt)
./
Secretary
AGREEMENT
00500-3
, ..
, ., ,
CUMBERLAND VALLEY MIDDLE SCHOOL 201-91
(Individual Contractor)
(SEAL)
(Hame of Individual)---
Trading and Doing Business as
Witness:
-.---------------.-.---.-.....-.....-.-.-------------------------------------
(Partnership Contractor)
(Name of Partnership)
Witness:
BY: (SEAL)
Partner
BY: (SEAL)
Partner
BY: (SEAL)
Partner
BY: (SEAL)
Partner
-----------------------------------------------------------------------------.
(Corporation Principal)
~~
nt) Secretary
(Corporate Seal)
OCI Construction Company, Inc.
(Name of Corporatiqo)
BY: ~~<t~~~~~rJ
Shane A. Miller
AGREEMENT
00500-4
..
....~"UI.\lu.\ ...'n"'~ Ill" ......uID (!)
..
J
",
I'
"1>'
,'_....:'
-'""'-,
"d'<J;Hl~;4i{i;~,i;",';'::ii;,+J';U,$"~~,;~~~#""""_~M~'''. 0> ( t..
,'\'
,
t'"
".
nr
; I. it
I I;
I;.
I '
I
Exhibit C
.
.. "
I ,
.
, ,
.
FI.LE.
., .
.'
July 14, 199J
,
Mr. Ed Haldeman
Cumberland Valley Middle
6746 carlisle pike
Mechanicsburg, PA 17055
Re: cumberland Valley Middle School
School
Dear Ed:
Per our conversation last week regarding compact,ion results, please
be advised of the following:
Prior to starting construction, CCI construction company
requests copies of all compaction tests taken at the building
pad. In reviewing the site operations to-date, CCI is under
the impression that compaction tests are only being taken at
the top of the backfilled areas. In accordance with the
contract specifications, compaction results should be taken
with every lift/layer of backfill material. with this in
mind, CCI requests that select areas of backfill be excavated
and tested ~o ensure proper compaction.
In addition, once the building pad is'ready to be turned over
for construction, CCI asks that the cumberland Valley school
District sign below and return this document acknowledging
that the building pad meets all Architect and Engineer
requirements and is acceptable for the start of building
construction.
I .
.~ llf Gettysblrg Rend
~btrg, P/\ 17055
F~: (717J 975-5640
"" (717) 975.2650
. I I .
. .. . .
.
.
.
.
, .. .
VERIFICATION
I verify that the statements made in the foregoing document
are true and correct to the best of my knowledge, information and
belief. I understand that any false statements made herein are
subject to the penalties of 18 Pa.c.s. 54904 relating to unsworn
falsification to authorities.
~UC6:
SHANE A. MILLER, ,
Senior Vice President, CCI
Date:
!'
-,. M ~-
i~ <"\,! ~-:;:
I_co , ..
l.t1r~ .J. .
G L)': - . );:.':
,...( :C ~.) ~~,
'- ..;.;: 0"
1:.-, '.
U' i~
, :
c :~? ,;~ ~- ':
t~_:. ./.
'.-'
.~ , <:, 'i 'j
,-
,-- w.) .~~.
W-
I' I ,., ::]
, ,:.) (J
if
62. Admitted. By way of further reply, CCI incorporates
its response to paragraph 61 above.
6J. Denied as a conclusion of law. By way of further
reply, CCI incorporates its response to paragraph 61 above.
64. Denied as a conclusion of law.
65. Denied as stated. It is admitted that on June 16,
1993, CCI and the District entered into a prime contract for the
general construction of the New Middle School Project. It is
further admitted that each party's responsibilities were governed
by the terms of the Contract Documents. All other averments are
denied as conclusions of law.
66. Denied. The averments in paragraph 66 of the New
Matter lack specificity. By way of further reply, CCI's work was
performed in accordance with the terms and provisions of the
Contract Documents. The remainder of the avsrments of paragraph
66 of the New Matter are denied as conclusions of law.
67. Denied as a conclusion of law. By way of further
reply, it is specifically denied that CCI breached any portion of
its contract with the District.
68. Denied as a conclusion of law.
69. Denied as a conclusion of law.
70. Denied as a conclusion of law.
71. Denied as stated. It is specifically denied that the
responsibility for coordination of the work among the prime
contractors on the construction project was vested in CCI by the
Contract Documents. By way of further reply, the responsibility
2
for coordination of the work among the prime contractors on the
construction pl'oject was specifically retained by the District
pursuant to paragraph 6.1.J of Article 6 of the General
Conditions of the Contract for construction. All further
averments are specifically denied, and strict proof is demanded
at time of trial.
72. Denied. It is specifically denied that the contract
documents required CCI to perform the coordination of the work
among the prime contractors. By way of further reply, CCI
incorporates its response to paragraph 71 above.
WHEREFORE CCI respectfully requests that judgment be entered
in its favor, and against Defendant District for the full amount
demanded in its Complaint.
COu.rBRCLAXM
7J. CCI incorporates its responses contained in paragraphs
60 through 6J above as if set forth here in full.
74. Denied as a conclusion of law. By way of further
reply, the District's active interference in CCI's work as
alleged in paragraphs 1 through 57 of CCI's Complaint, which are
incorporated herein be reference, renders Section 8.J.3
inapplicable to CCI's claims.
75. Denied. By way of further answer, CCI incorporates its
response to paragraph 74 above.
76. Denied. By way of further answer, CCI incorporates its
response to paragraph 74 above.
J
77. Denied. By way of further answer, CCI incorporate. it.
re.pon.e to paragraph 74 above.
WHEREFORE CCI respectfully requests that jUdgment be entered
in its favor, and against Defendant District, for the full amount
demanded in its Complaint.
POWELL, TRACHTMAN, LOGAN,
CARRLE & BOWMAN, P.C.
By
C. Gra nger
I.D. #15706
Michael W. Winfield
I.D. #72680
114 North Second Street
Harrisburg, PA 17101
(717) 2J8-9300
Date: June 6, 1996
4
I' r' 0,
r "
L: ,
I , , .
I~ " .,
, ~ ~ ,
I !
i 'J
,.. 'I.
f' \,') :./
t.: - U
..
0
; " ~ !
c
! ~ Z
. c 0
j ~ .. :; 0
.. ::l 0 .. II
Z ~ . <( VI .-
:J",u~i I ~
a ti ~ II ~
:> a ~ ~ :S iii
i I: cox ~
. < 0 .. ~
>. 0 0 W
~ ,... ta D
~ N :5
i
..
.t__.. ,.
,..
-
~
. ~I~~H~SHERIFF.~ OFFICE
SHERIFF SERVICE
PROCESS RECEIPT,end AFFIDAVIT OF RETURN
50 NORTH DUKE STIlEET. LANCASl EA. PENNSYLVANIA 171102 . 1717) 21m \1200
.--.---- ~- -.....-. .,---.,.--,...-.-,--.--.----. ~
INs-rAUCTIONS FOR SERVICE OF PROCESS on u~ f.~.'" of the lal tNo.
5) copy 01 Ihlt lrnm PIt... t'r~ Ql' pMl IItglbly Do M dltach lI'ly coptS
8
---:!!
2 counT NUMllll(---~--
t. PLAINTIFF/51
Cumberland valley_sE!1()()l_~!",-trlc-L . ...96~llQ.Civil. .
3 DEFENDANT/51 .1 I YI't: m WllIT 0" COMl't AINT
The Ray Group, Inc.._..__________.__.____.._._._ _ . _. ..._. __._..._._ __WriLta_Join_Addtl-..Oef..____i::
SERVE { 5 NAME OF INDIVIDUAL. COMPANY. COIU'OIlAIION [tC. TO liE UEIWEO ~
. ~~~DA~5~~511~1~?f~tr-!APJi1~%~).-C~.V~-k)i;;.1:;I-J-.. sl~i"lilmllll)C'oijo)M- .-.. ...-- - ----- --.-- -------"-- ~
AT 127 Eas t Ora!!'3!!_.? t r~~. t.,_LiJ!1.c~_f!.t.9!'.!__.!'__~_I.'7..60.1.____~~__________.____..___
7. INDICATE UNUSUAL SERVICE COMMON OF PA DEPUTIZE OIHE" Cumherl and
Now, __ Jo'eb. 14 19 __~~~:::-:i:-SHERIFFOFI!~\(~COUNTY, PA, d~ti';;bYd~P~lilOlhe sl;~;;iioi'--.----.--._-
----1&ru:D.13ll r ... .." ._.__._._ Co un IV to oxoculo litis '0!I.i!P'~"2:~I"Olurn thereof l)II~~
to lew. This depulnlion being mode otllto requost nndnsk oltlto plmnlill. .. --:r::."".....ci"',,;.r.f.'n?::t,;\t:./;~------"----
S. SPECIAL INSTRuc'iIONS.O'R"Di"ER INFORMATION'i"AT WILL ',,'SSIST IN'EXPEDITINO SERVICE: ... .. ........" ~ - .
NOTE ONLY APPLICABLE ON WRIT OF EXECUTION: N.B. WAIVER OF WATCHMAN. Any IIHpulV shulIlI IIIV}'IIIO upon or uMehlng uny property undor
within wnl may leavlt r.amo wllhoul a wlIlchmlln. III cU51ot.ly 01 whomovot IS lound m p05S11l>!>lon. illlor notllYlng pOIson 01 levy or nllachmonl, wllhoulllabl1ily on
the part 01 such doputy or 1110 .honlllo any plalnllll hOlCln 10f . ~. daatl Ion tlt fI.lIllOW\1 01 uny such propmty bololO shonlfs aalo thlllool
S. SIGNATURE 01 ATTORNEY OJ o'ho' DRIDINATDR . M. D'-;;~.'''.;;-.~;a'~ TE.LEPHONE NUMUER =CATE
Richard Snelbaker ESQ. AT SNELBAKER & BRENNEfAW-697-8528 2-13-96
12. SEND NOTICE OF SERVICE COpy TO NAME AND ADDRESS BELOW:(Thiaarean;ulib';-C:ompleled ir "011C11110 b. maned)
I
44 W MIiN ST. I MECHANICSBURG._J'.~_.J.IP??=-Q3J.e
SPACE BELOW FOR USE OF SHERIFF ONLY - 00 NOT WRITE BELOW THIS LINE
NAME 01 AulllOfllOIJ Lcsoo;;j;;;!VOI-CIO~----- 14, Qalo ROcOl....od 15
E)lpllllhonIHOllflng dale
13. I acknowledge recclpt ollha Writ}
or compl.,nl R. 'nd"Rlod 0"ovo..J.(J!l.\'._foI9.R!u:,s_.~95..3609. .... ._. ._. _ . ._._." _.2~15-96___ ~_t.4ft96
16 I horeby CERTIFY and RETURN thai I hllvo pl1ll>llnnUy SIlf\ltlil, ~h;l\Ie l!lglll UVlth~nt:u 01 SIHVICU II:> tihown III -nllmarks., hnvo Oll!culcd tiS shown in
"RomOl"", tho wrll or complainl doscllhcd on Ihll mdl'.llllu:lI, COIll~IV. CorPllfllltoll nle, ill 11m ,lddf{!!is shol'rn ahuve Of on tho indIVidual, company. foot.
porallon. ele, ollha addlO!i8 IJlserted bolow by hnmJuIO II TRUE and AnESTED COPY thereal.
17. I homily cCltlfy nnd telum n NOT FOUND bm;ilU!iO Imn unable lu loc;llu!lll! Ulclwnhl,ll. compillly, CflfjlOfilhlll, tJlc, flallllld uhovo (Seo lemnlk~ helow)
'5 NRmo Rnd 1,110 01 ",d,,,dIlRI ..,vod ,,1 '1:j'mwn 01;';;oTlli"~ldt,on;,",liC7~.;"':;.';ii""'. -.'-:.. -- ). .--ro . I~'~O" 01 ,","h.. "0. ",' "'~..,'.,
M .c:....kAt.. ~,,~A__ _ =o_IJ_____.._ .r_fle.StJ_~~_i_~_____ ~~:~IO:;;Si~:~O III ItlU tlolond.lllla IllHml
20 Add,." 01 who,. .d'd Icomplo.o onIV" d'li~,"n shown "ho'''1 t ''''0' 01 "FO. AI''''''''"''' NO. C,'V. !lOlO. T.p 21 Dalo 01 S "'''0 22. Tlmo
Slalo ond Ztp Cocln) II
;)/ (5 ~
-
PM
eST
...
30...Ml__
Dep.,nl.eO'O] MII"Ti.;p.,n'I~'leIMII" Oep.lnl.
26 :",y cr."__L~t.:r6 F 132~05-
Dep.lnt.
23 ATTEMPTS
Mil..
-
.5
OeP~tJ_ Dei.
25. SOrvlCO C051s
24 Advanco Cosls
a84319
30 REMARKS,
100.00
~ /. .,~"j
d ft-'f93
zP(, h b
STA:
----,:;D-.-P---
31 AFFIRMED nnft lluhSCflhml 10 holoro mo tillS ~~______.___n
: dRV 01 -rL~trf:5 -'~ - -" .f)~ Cl.lL=.==_
i~~UCII\lIVN'llilr'" p,)~
MY COMMISSION EXPIRES
38 I ACKNOWLEDGE RECEIPT OF THESHERIF~BRETUAN'SIGNATUR-E}'-- .~--.
OF AUTHORIZED ISSUING AUHtORITY AND TITLE
---~~---~~,-'--_._---------'~--
NC
~"16I1OC8IVIl'J
lcsn. I . '911 Amtllllltld \!}<Jj
I ISSUING AUTHClHI J Y
. .
~
C'I
..;t' '~ct
0 c2
J
ill ~ l , i:....h;"'. !...~~~tf;
...., :';i; 0
.- '(J
uJ
0 In '0
ill C\:l j3
0: w .- it~
&...- 05
\.0
C'I
. ,.
~--.
CCI CONSTRUCTION COMPANY, INC. : IN THE COURT OF COMMON PLEAS
Plaintiff CUMBERLAND COUNTY, PENNSYLVANIA
.
.
v.
.
.
CUMBERLAND VALLEY SCHOOL
DISTRICT
: NO. 1996-110 Civil Term
Defondant
v.
.
.
THE RAY GROUP
Additional Defendant
.
.
.
.
PETITION POR LEAVE TO AMEND COMPLAINT
CCI Construction Company, Inc. ("CCI"), by and through its
attorneys, Powell, Trachtman, Logan, CarrIe & Bowman, P.C.,
hereby petitions this Court for leave to amend its Complaint, and
in support thereof avers the following:
1. On January 5, 1996, CCI filed its Complaint against
Defendant Cumberland Valley School District ("District").
2. On January 16, 1996, service upon the District was
offectuated by the Sheriff of Cumberland County.
J. On February 2, 1996, the District entered its
appearance by filing Preliminary Objections to the Complaint.
4. Among the objections interposed by the District was a
preliminary objection in the nature of a demurrer to CCI's claim
for attorney's fees. ~ paragraphs 5 and 6 of District's
Preliminary Objections.
CERTIFICATE OF SERVICE
AND NOW, on March 15, 1996, I hereby certify that I have
served a true and correct copy of the within Petition for Leave
to Aaen4 Co.plaint upon the following person(s) and by regular
first class United States mail, postage prepaid.
Richard C. Snelbaker, Esq.
44 W. Main Street
Mechanicsburg, PA 17055
Attorney for Cumberland Valley School District
R. Thomas McLaughlin, Esq.
Kelly, McLaughlin & Foster
1700 Atlantic BUilding
260 S. Broad Street
Philadelphia, PA 19102-5092
Attorney for The Ray Group
~
'.. \,J
I - 17'
,oJ '-
I ..
tl..1 ~. - 1",,-
r:l . "
.. .
tC:i :. ~\ I
lr ~. .j
f,: r:>
G'~ \ (0) ,
r< : ',i
I : 0 : I .u..
I', l.'l )
L- ,,~ . ()
,"A.
~'1
~
.;t
ll'j
'1
~
t
~
CERTIFICATE OF SERVICE
AND NOW, on March 15, 1996, I hereby certify that I have
served a true and correct copy of the withi~ Pr..cip. tor Li.tinq
c... tor Arqua.nt upon the following person(s) and by regular
first class United States mail, postage prepaid.
Richard C. Snelbaker, Esq.
44 W. Main Street
Mechanicsburg, PA 17055
Attorney for Cumberland Valley School District
R. Thomas McLaughlin, Esq.
Kelly, McLaughlin & Foster
1700 Atlantic BUilding
260 S. Broad Street
Philadelphia, PA 19102-5092
Attorney for The Ray Group
C~:&B~
Complaint to withdraw i1s request for allomey's fees. Concurrently, CCllisted the remaining
objections for argument before this Court. On March 20. 1996,this Court (per Order of Hess, 1.)
granted CClleave to wilhdraw its claim for allomey's fees. In accordance therewith, CClliIed
its First Amendment to Complaint on or about April I, 1996,
On April 8, 1996, CCI received the District's Briefin Support of its Preliminary
Objections, CCI now files this Briefin Opposition thereto.
II. ISSUES PRESENTED
A, WHETHER CCI'S COMPLAINT COMPliES WITH THE SPECIFICITY
REQUIREMENTS OF PA.R.elV.p. NO. IOI9(a)?
(Suggested Answer: Yes)
B, WHETHER eCI's COMPLAINT HAS COMPliED WITH THE SPECIFICITY
REQUlRFMENTS WITH REGARD TO DAMAGES?
(Suggested Answer: Yes)
C. WHETHER CCI'S COMPLAINT SETS FORTH A CLAIM FOR DELA Y
DAMAGES UPON WHICH REliEF MA Y BE GRANTED BY THIS COUR'/?
(Suggested Answer: Yes)
D, WHETHF.R CCI'S COMPLAINT PROPERLY STA TES A CLAIM UPON
WHICH RELIEF MA Y BE GRANTED DUE TO THE D1S7'RICT'S '
FAILURE TO COORDINA TE THE MULTIPLE CONTRACTORS' WORK
ON THE PROJECn
(Suggested Answer: Yes)
J
c.
CCl's Complaint Complies With The Specifici~ ReQuire,:e~~s ~:The
Pennsvlvania Rules Of Civil Procedure With ReLlard To D II
The District's second objection to CCl's Complaint alleges that CCI has "fail[ed) to
comply with Pa.R.Civ.P. 1019(1) in that items of special damages have not been specifically
stated." S.el: District's Preliminal)' Obiections at ~14. Special Damages are damages that are not
directly related to plaintill's cause of action; that are not the usual and ordinary consequence of
the wrong done, but depend upon special circumstances. S.el: Weinllard v Fischer & Porter Co.,
47 D. & C.2d 244, 249 (C.P. Bucks 1968); Standard Pennsylvania Practice 2d ~ 16.65 (1994).
CCI disputes the District's allegation that the damages it seeks are other than those which
nOllnaJlyand ordinarily arise from a delay claim on a construction contract. Nevertheless, CCI
has pled its damages with sufficient specificity so as to set forth its right thereto, and to afford
the District the opportunity to defend itself. As set forth 2U!DI, that is all that is required under
Pennsylvania procedure. Accordingly, the District's objection should be denied.
D. CCI Has Set Forth A COllnizable Claim For MonetalY Delay Damaves.
Notwithstandinll Article 8 3.3 Of The Contract
In its third objection (in the nature of a demurrer) the District asserts that, based upon
,
Art. 8.3.3 of the Contract, CCI has waived any rights to recover monetary damages for delay.
The Districts waiver theory, however, rises and falls upon the application of Art. 8.3.3 to the
actions and omissions of the District complained of in CCl's Complaint. As set forth below, the
District, based on the facts as pled by CCI, cannot invoke Art. 8.3.3 as a defense to CCl's claims.
Pennsylvania courts have routinely refused to enforce contract clauses which limit a
party's liability; particularly "no damage lor delay" clauses similar to Art. 8.3.3 of the Contract
6
in this case. The rule in Pennsylvania is that exculpntory provisions in a contract cannot be
raised as a defense where (I) there is an affirmative or positive interference by the owner with
the contractor's work, or (2) there is a failure on the part of the owner to act in some essential
matter necessary to the prosecution of the work. Coatcsvillc Contractors & Enllineers. Inc v.
Boroullh ofRidh:y Park, 509 Pa. 553, 506 A,2d 862 (1986); Gasoarini Excavatiml Co v
Pennsylvania Turnpike Commission, 409 Pa. 465, 187 A.2d 157 (1963). Under such
circumstances, the interference and/or omissions by the owner are deemed to be outside the
contemplation of the parties at the time the contract was entered into, and therefore delay
resulting therefrom is not subiect to waiver. S.el: Coatesville. ~ 506 A.2d at 867.
/--:.::=:. --- -,
~n Coatesville Contra~~rs.~oroullh of Rid lev Park,~, the Pennsylvania Supreme
Court held that a contractor could assert a claim for additional compensation in excess of the
actual price against the owner, notwithstanding the presence of a "no damage for delay" clause
in the contract. The contract called for the contractor to remove salt from a lake bed. Prior to
the job being initiated, the lake was drained, and the specifications in the contract provided that
it would remain in that condition until all silt removal work had been completed. However, at
the time the plaintiff was required to perform the work, water covered the site, occasioning extra
expenses in the performance of the contractor's scope of work. Ill, 506 A.2d at 863-864.
The parties' contract included a "no damage for delay" clause which is analogous to, if
not more onerous than, Art. 8.3.3 of the CClmistrict Contract. The Coatesville contract
provision provided, in relevant part:
The Contractor shall not be entitled to any claims for damages from any
hindrance or delay from any cause whatever in the progress of the work,
or any portion thereof, but when such hindrance or delay results from
causes entirely beyond the control of the contractor, said hindrance or
7
stated a claim upon which relief may be granted. Accordingly, the District's objection should be
denied.
IV. CONCLUSION
For all the foregoing reasons, Defendant Cumberland Valley School District's
Preliminary Objections should be denied, and Defendant should be ordered to file a responsive
pleading to the Complaint.
POWELL, TRACHTMAN, LOGAN,
CARRLE & BOWMAN, P.C.
By (J Ji. L
c.Grainger~
I.D. #15706
Michael W. Winfield
I.D. #72680
114 North Second Street
Harrisburg, PA 17101
(717) 238-9300
Date: April 12, 1996
12
,
..')If,/ Cl/hcO !10., O'f'\a.. C.t41 ~
IN THE COURT OF COMMON PLEAS OF ~_,_~,: U1D"/t'2;'L
CUMBERLAND COUNTY, PENNSYLVANI~~' ~2 f-c 0J'
V1J.!l, ,.11 ") \Ct/,' :: ..nVv~
0\ '';''lA.(!V CCI CONSTRUCTION CO., /\V!.\d. ~\J--
X ~r'. Plaintiff ~
'l~l\ Vn
NV tJ: vs.
-f ~.. IJ {UMBERLAND VALLEY SCHOOL
tJ ,ay DISTRICT,
) Defendant
cJAf}J.
THE RAY GROUP,
Additional Defendant
No. 96-110 CIVIL TERM I ,_
r
1)' (
CIVIL ACTION - LAW U ~
- rJ. (
) I~
JURY TRIAL DEMANDED )r.U~(tJL"\~l
I, lJ
'. \"
. (~lla' ~AIV'
:\ l
DEFENDANT CUMBERLAND ~~~LEY SCHOOL DISTRICT'S \.
BRIEF IN SUPPORT OF ~~~LIMIN~~~ OBJEC~10NS
TO PLAINTIFF'S COMP~!NT
vs.
PROCEDURAL AND FACTUAL BACKGROUHQ
CCI Construction Company (IICCIII) initiated this
umberland Valley School District (IIDistrictll) was served with
the Complaint on or about January 16, 1996. The District filed
timely preliminary objections to Plaintiff's Complaint on
a Complaint on January 5, 1996. Defendant
LAw O'''CEIl
SNELBAKER
1\
BRENNEMAN
February 2, 1996.
District joined The Ray Group as an additional defendant by
Writ issued on or about February 13, 1996 and served February 15,
1996. CCI filed a Petition For Leave to Amend Complaint on or
about March 15, 1996 which, inter alia, sought to drop its
request for attorneys fees. By Order dated March 20, 1996, this
Court granted CCI's Petition and ordered CCI to amend its
Complaint within 20 days of service of the Order. By letter
LAW O....ICE.
SNELBAKER
a
BRENNEMAN
dated April 1, 1996, CCI filed its First Amendment to Complaint
which withdrew its claim for attorney's fees.
This case involves the construction of a new Middle School
for the District. (Complaint, Paragraph 4.) On June 16, 1993
CCI and the District entered into a contract for the general
construction of the new Middle School. (Complaint, Paragraph 9.)
Article 8.3.3 of the contract between CCI and the District
provides:
No payment or compensation or claim for damages
shall be made to the Contractor as compensation for
damages for any delays or hindrances from any cause
whatsoever in the progress of the Work, notwithstanding
whether such delays be avoidable or unavoidable. The
Contractor's sole remedy for delays shall be an
EXTENSION OF TIME ONLY, pursuant to and only in
accordance with this Paragraph 8.3, such extension to
be a period equivalent to the time lost, by reason of
any and all of the aforesaid causes, as determined by
the Architect. In consideration for this grant of a
time extension, the Owner and the Architect shall not
be held responsible for any loss or damage or increased
costs sustained by the Contractor through any delays
caused by the Owner or Architect or any other
Contractor or on account of the aforesaid causes or any
other cause of delay. In the event the Contractor
shall choose to litigate this clause or issue and loses
said litigation, the Contractor shall reimburse the
Owner and the Architect for their reasonable attorney's
and expert witness fees and all other costs and
expenses incurred by them in the litigation.
Despite the clear language of 8.3.3 set forth above, CCI has
brought this action for damages.
II. ISSUES PRESENTED
A.
Whether the Complaint is insufficiently specific?
(Suggested answer: Yes.)
-2-
B. Whether the Complaint is insufficiently specific
with regard to special damages?
(Suggested answer: Yes.)
C. Whether CCI is barred from seeking monetary
damages for the alleged delays by Section 8.3.3 of
the contract?
(Suggested answer: Yes.)
D. Whether CCI had responsibility to coordinate work
and contractors under the contract?
(Suggested answer: Yes.)
III. ARGUMINT
A. THI COMPLAINT 18 IH8UrrICIINTLY 8PICIrIC.
Pennsylvania is a fact-pleading jurisdiction. Smith v.
Brown, 283 Pa, Super. 116, 423 A.2d 743 (1980); Pa.R.c.p.
1019{a). A complaint must formulate the issues by summarizing
the facts essential to support the claim. Smith, 423 A.2d at
745. Mere conclusions are not sufficient to plead a cause of
LAW 0'''(:1:0
SNELDAKER
It
BRENNEMAN
action. Where a party fails to plead specific facts in the
complaint, those claims are properly dismissed. Hornunq v.
Schauseil Insurance, 422 Pa, Super. 472, 619 A.2d 775. When
these pleading requirements are applied to the vague and
conclusory averments of the Complaint, it is apparent that the
Complaint is insufficiently specific.
In paragraph 17 of the Complaint, the "agents or other prime
-3-
LAW OI"P1CU
SNELBAKER
a
BRENNEMAN
contractors of the District" are not identified and there are no
facts pleaded to indicate the manner in which these unidentified
entities allegedly caused a delay. In paragraph 18, CCI fails to
identify the subcontractors alleged to have scheduling conflicts
and fails to plead any facts surrounding the alleged conflicts.
Pa.R.C.P. 1019(f) provides that "[a]verments of time, place
and items of special damage shall be specifically stated." In
paragraph 21, CCI fails to plead the dates and extent of the
allegedly untimely performance by the Sitework contractor. Such
failure is a direct violation of Pa.R.C.P. 1019(f). Similarly,
CCI fails to plead the places of the alleged design defects and
errors referred to in paragraph 22.
In Paragraph 23(e), CCI makes a vague reference to its
"critical path activities" being "adversely impacted". Such a
statement is conclusory and fails to set forth material facts to
support such a conclusion. In paragraphs 24 and 25, CCI refers
to an "unanticipated and unreasonable increase in Project costs
and time for completion" without setting forth a factual basis
for the alleged increases.
In paragraph 26, CCI fails to indicate the alleged sequence
of the work which it avers was broken and further fails to
identify the work that was alleged to have been performed out of
sequence. In paragraph 27, CCI does not plead material facts
sufficient to identify the manner and extent to which the Site
contractor allegedly failed to perform in a timely manner.
In paragraph 40(a), CCI fails to identify its alleged
-4-
sidew4lk work in the Courtyard. In paragraph 40(b), CCI does not
aver the location and manner in which the prime Plumbing
contractor and prime Electrical contractor were allegedly
disrupted. In paragraph 40(c), CCI fails to aver material facts
to specify the "serious impact" which it allegedly sustained in
its schedule. Paragraph 40(d) does not set forth the alleged
disruptions in the schedules of Site contractor, Electrical
contractor and Mechanical contractor.
I-AW O"lI::U
SNllnAICl:ft
It
BRENNEMAN
Paragraph 41 is insufficiently specific for failure to aver
facts to support the conclusions averred as "unrealistic
construction SChedules", "problems caused by the District, The
Ray Group and other prime contractors", the "District's
unilaterally ordered milestones", the alleged "disruption to the
progress of CCI's contract work" and the alleged "additional
costs". In paragraph 56, CCI fails to aver facts to indicate
which of the enumerated alleged actions and omissions were caused
by the District, The Ray Group and/or other prime contractors.
In paragraph 58, CCI fails to indicate the dates comprising
the "20 weeks" in A.1, 2 and 4; the "6 months" in A.3; the "5
months" in A.5, 6, 7, 8, 9, 10, 11 and 12 and the "140 calendar
days" in B. CCI also fails to set forth in paragraph 58 the
composition of its various alleged damages such as the number of
hours, number and identity of persons performing services,
amounts actually spent on utilities, office sUpplies, truck
expense, overhead, snow removal and costs to remove and replace
concrete slabs.
-5-
LAW O"ICE5
SNELBAICER
81
BRENNEMAN
In order for the District to fully understand CCI's claims
and formulate a meaningful response to the Complaint, it is
necessary for all of the above deficiencies in pleading to be
corrected.
B. THE CONPLAINT IS INSUFFICIENTLY SPBCIFIC
WITH REGARD TO SPBCIAL DAMAGES.
The specific deficiencies set forth in the foregoing section
of this brief are incorporated herein by reference. Those
include references to special damages which must be specifically
pleaded. Pa.R.C.P. l019(f). Special damages are those which
arise from the special circumstances of a case. Gooclrich-Amran
2d. S l019(f):6. As this action represents unique circumstances,
the alleged damages are special and must be pleaded with
specificity.
The summary of alleged damages in paragraph 58 of the
Complaint does not specifically set forth the number of hours,
the number and identity of persons performing services, the
amounts actually spent for utilities, office supplies and truck
expense, overhead snow removal and costs to remove and replace
concrete slabs. As these items are special damages, they must be
set forth with specificity in the Complaint.
C. CCI IS BARRED FRON SEEKING NONETARY DAMAGBS BY
SECTION 8.3.3 OF THE CONTRACT.
Supplemental Condition section 8.3.3 of the General
Conditions of the Contract for Construction provides:
No payment or compensation or claim for damages
shall be made to the Contractor as compensation for
-6-
damages for any delays or hindrances from any cause
whatsoever in the progress of the Work, notwithstanding
whether such delays be avoidable or unavoidable. The
Contractor's sole remedy for delays shall be an
EXTENSION OF TIME ONLY, pursuant to and only in
accordance with this Paragraph 8.3, such extension to
be a period equivalent to the time lost, by reason of
any and all of the aforesaid causes, as determined by
the Architect. In consideration for this grant of a
time extension, the Owner and the Architect shall not
be held responsible for any loss or damage or increased
costs sustained by the Contractor through any delays
caused by the Owner or Architect or any other
Contractor or on account of the aforesaid causes or any
other cause of delay. In the event the Contractor
shall choose to litigate this clause or issue and loses
said litigation, the Contractor shall reimburse the
Owner and the Architect for their reasonable attorney's
and expert witness fees and all other costs and
expenses incurred by them in the litigation.
By entering into the construction contract with the
District, CCI waived its rights with regard to recovery of
monetary damages for delay. Waiver is the voluntary and
intentional abandonment or relinquishment of a known right.
Samuel Marranca General Contractinq Co. v. Amerimar, 416 Pa,
Super. 45, 610 A.2d 499 (1992). The averments of the Complaint
and the language of Section 8.3.3 of the contract indicate that
all of the elements of waiver have been met.
First, there is nothing of record that would suggest that
CCI's contract with the District was not voluntary and
intentional. Second, the language of 8.3.3 indicates that CCI
was aware of its right to remedies other than an extension of
LAw O"ICtB
SNELBAKER
81
BRENNEMAN
time. Third, CCI abandoned or relinquished its right to other
remedies by entering into the Contract where the parties
expressly exchanged an extension of time in consideration for the
Owner and Architect not being held responsible for monetary
-7-
damages for delay. The Section even provides for payment of the
Owner's attorneys' fees in the event the Contractor litigates
met.
this point and loses. All of the elements for waiver have been
The District is Unaware of any case law interpreting the
precise contract language at issue in this matter. Although some
Pennsylvania cases have held that "no damages for delay" clauses
were unenforceable under certain fact situations, different
contract language and different factual circumstances compel a
contrary result. In the case of Sheehan v. Pittsburah, 213 Pa,
133, 62 A. 642 (1905), the city failed to obtain the complete
right-of-way necessary to undertake the project. The contract
was based upon the assumption by both parties that the right-of-
way had been properly secured so that work could begin and
proceed without interruption. Under such facts, the Court held
that "[nJotwithstanding the breadth of the language of the
agreement that all loss or damages from unforeseen obstructions
and difficulties and from delay, were to be borne by the
contractors, it is clear that the delay from the city's failure
to obtain complete right-of-way was not in the class of
difficulties and delays which were in the minds of the parties,
for the agreement was based on the assumption that the right-of-
way had been secured . .
" 213 Pa, at 134.
LAw a"lcca
SNELBAKER
a
BRENNEMAN
In the case at bar, the Complaint does not set forth any
claim which would fall into the category of being outside of the
class of difficulties or delays in the minds of the parties at
-8-
the time the contract was entered into. Thus, the situation ~
iUdice is distinguishable from the Sheehan case and its progeny.
Further distinguishing our scenario from the Sheehan case is the
language of Section 8.3.3. Section 8.3.3 specifically sets
forth, inter alia, that U[iJn consideration for this grant of a
time extension, the Owner and the Architect shall not be held
responsible for any loss or damage or increased costs sustained
by the Contractor through any delays caused by the Owner or
Architect or any other Contractor. . ..U An extension of time
is the sole remedy provided for in Section 8.3.3. Because the
clear language of Section 8.3.3 evidences the Contractor's
voluntary relinquishment of a known right, CCI cannot now claim
damages. Such a result would be contrary to the express language
of the contract.
In the Complaint, CCI seeks damages against the District
based upon the acts or omissions of "other contractors".
Examples are found in paragraphs 17, 21, 40 and 56 of the
Complaint. CCI's request for damages against the District for
the alleged acts and omissions of other contractors is clearly
barred by Section 8.3.3. In the case of Henrv Shenk COmDanv v.
Erie County, 319 Pa, 100, 178 A. 622 (1935), the Pennsylvania
Supreme Court rejected a contractor's claim for delay damages
where the contractor alleged losses due to the acts of the
LAW a"ICt8 architect and other contractors. These delays found to be
SNI!:LBAKER were
lit
BRENNEMAN within those contemplated by the clause in the contract
-9-
LAw O'PlCU
SNILBAICER
a
BRENNEMAN
addressing Delays and Extension of Time.. When toe reasoning
employed by the Court in Shenk case is applied to the case ~
iUdice, it is clear that CCI's claims based upon the alleged acts
or omissions of the Architect and other contractors cannot be
sustained in light of the language contained in Section 8.3.3.
Other Pennsylvania cases decided after the Henrv Shenk Co.
case discussed above reached contrary results under different
facts. However, cases such as GasDarini Excavatinq v. Pa,
TurnDike Comm., 409 Pa, 465, 187 A.2d 157 (1963), Pa, DeDt. of
Hiqhwavs V. S.J. Groves, 20 Pa, Cmwlth. 526, 343 A.2d 72 (1975)
and C.J. Lanqenfelder & Son v. Pa, DeDt. of Trans., 44 Pa,
Cmwlth. 585, 404 A.2d 745 (1979) are based upon fact situations
distinguiShable from those in the case at bar. In the Gasoarini
case, the Turnpike Commission gave the contractor a notice to
proceed in June, 1955 but another contractor was then engaged in
drilling and slushing on the same stretch of road. This
prevented the plaintiff-contractor from working on the site until
November, 1955. The Court held that a paragraph of the contract
requiring cooperation with the Slushing contractor did not bar
Footnote No.1: Article 18. Delays and Extension of Time. _ If
the Contractor be delayed at any time in the progress of the
work by any act or neglect of the Owner or the ArChitect, or
of any employe of either, or by any other Contractor
employed by the Owner, or by changes ordered in the work, or
by strikes, lockouts, fire, unusual delay in transportation,
unavoidable casualties or any causes beyond the Contractor's
control, or by delay authorized by the Architect pending
arbitration, or by any cause which the Architect shall
decide to justify the delay, then the time of completion
shall be extended for such reasonable time as the Architect
may decide.
319 Pa, at 103-04
-10-
LAW O"ICU
SNnSAKER
III
BRENNEMAN
Gasparini from collecting delay damages. There are no comparable
averments in CCI's Complaint and Section B.3.3 is much more than
a "cooperation" clause. In the S.J. Groves case, the Department
of Highways was found to be liable to a contractor for the
increased cost of completing a contract where the Department
knew, but failed to disclose, that the contractor would not have
access to a portion of the site for some 14 weeks. S.J. Groves,
343 A.2d at 75-76. As there are no averments of undisclosed
conditions in CCI's Complaint, the holding of the S.J. Groves
case has no application to the issues at hand.
The Lanoenfelder case is also based upon facts which are
materially different from those sub iudice. In Lanoenfelder, an
environmental permit issue delayed the project for seven months,
the redesign of a temporary street bypass delayed the project by
nine months and a problem with concrete delayed the project
several more months. A Board of Arbitration awarded the
contractor delay damages and the Commonwealth Court affirmed.
The Court refused to change the Board of Arbitration's findings
of facts regarding the Department assuring concerned citizens and
environmental groups that the construction activities through an
environmentally sensitive marsh would be limited to the right of
way. As it turned out, the Department then approved
Langenfelder's plans to dump sediment outside of the right of
way. As a direct result of the Department's actions, the
contractor was delayed some seven months as the environmental
permits were disputed. 404 A.2d at 705. There are no
-11-
allegations in the Complaint at bar that are remotely akin to
those facts in the Lanaenfelde~ case. Thus, the hOlding of that
case does not control dispOsition of CCI's claim.
CCI's Complaint goes so far as to attempt to collect damages
from the District due to the weather. (Complaint, paragraphs 29-
34.) Certainly weather conditions in general and snow in
particular were assumptions within the minds of the parties at
the time the Contract was entered into. Section 8.3.3 bars the
collection of damages for such delays. See, Sheehan vL
Pittsburaq, SUDr~. The claim by CCI based upon adverse weather
conditions illustrates the unreasonabless of CCI in attempting to
blame everyone but itself for delays encountered in the
construction project at issu~.
Based on the foregOing, the Complaint shoUld be dismissed as
legally insufficient pursuant to Pa, R.c.p. 1028(a) (4).
D.
THB COHTRACT PLACBS RISPOHSIBILITY POR
COORDIHATIOH OP WORK SgUARILY OH CCI AHD
HOT OH THB DISTRICT.
'j
the responsibility to Coordinate Work and contractors. The great,
;'
LAw O""'Cts
SNELBAkER
a
BRENNEMAN
Throughout the Complaint, CCI asserts that the District had
majority of CCI's claims appear to rest on this flawed premise.
The Contract provides that the responsibility for
Coordination of work and contractors is on the Contractor. This
theme is repeated in several sections of the contract. For
example, Section 3.3.1 provides:
3.3.1 The Contractor shall supervise and direct the Work,
uSing the Contractor's best skill and attention. ~
Contractor shall be solelv resDonsible fo~ and have control
-12-
'i-,
"
,j
L
r
I I.
i; it
III!
l'i.
, 1:
I
over construction means, methods, techniques, sequences and
procedures and for coordinatinq all Dortions of the Work
under the Contract, unless Contract Documents give other
specific instructions concerning these matters. (Emphasis
added. )
Section 4.23 provides, in pertin~nt part:
4.2.3 The Architect will not have control over or charge of
and will not be resDonsible for construction means, methods,
techniques, sequences or procedures, or for safety
precautions and programs in connection with the Work, since
these are solely the Contractor's resDonsibilitv as DrQ~!Qed
in ParaqraDh 3.3. The Architect will not be responsible for
the Contractor's failure to carry out the Work in accordance
with the Contract Documents. ...
These two contract provisions conclusively establish that
the Contractor, CCI, has sole responsibility for "coordinating
all portions of the Work" Clearly the District is not
responsible for such activities under the express language of the
contract. As a result, CCI has failed to state a cause of action
on whjch the relief sought can be granted and the Complaint
should be dismissed as being legally insufficient.
IV. CONCLUSION
For all of the reasons explained hereinabove, the
Defendant's Preliminary Objections to Plaintiff's Complaint
should be granted.
Respectfully submitted,
SNELBAK & BRENNEMAN, P.C.
/
Dated: April 5, 1996
~~/
ar C. Snelbaker
Pa, Sup. ct. I.D. #06355
44 West Main street
Mechanicsburg, PA 17055-0318
(717) 697-8528
Attorneys for Defendant
Cumberland Valley School District
LAW O'"cr:a
SNELB~KER
IIr
BRENNEMAN
-13-
CERTIFICATE OF SERVICE
I hereby certify that I am this date serving true and
correct copies of the within Defendant Cumberland Valley School
District's Brief in SUpport of Preliminary Objections to
Plaintiff's Complaint by sending the same by first-class mail
postage paid to the fOllowing persons addressed as follows:
c. Grainger Bowman, Esquire
Powell, Trachtman, Logan, CarrIe
& Bowman, P.C.
114 North Second Street
Harrisburg, PA 17101
R. Thomas MCLaughlin, Esquire
Kelly, MCLaughlin & FostAr
1700 Atlantic BUilding
260 South Broad Street
Philadelphia, PA 19102-5092
ard C. Snelbaker
Snelbaker & Brenneman, P.C.
Attorneys for Defendant
CUmberland Valley School District
Dated: April 5, 1996
LAw O""ICU
SNELIIAICEA
It
BRENNEMAN
._-----
.. -. - ... n_____
.. In
" ~ ~
r..< '" .. ..
0.... '" c:: 'tl f:j~ t:::
"'~ .,. .. " .;l ..;
.. 'tl .. ::lr..i;; I-: ..-.
~~ " " '''' UJ~ 7.
,,. OJ .. ..:w..: '" ~ :.:
.. '" '" ::"-H~ ~ ~~ t
1><'" .... S OJ e ~ ~ oj ~
15ffi:r. I>< '" .... oJ "
0 '" ~ H....p.. UJE ~ S .
. :I: " ::S"'t;l ;;: ~B ~ ;;
~I><el . U 0 " "'0 E 1 5
8 . '" , .... ffi '" <>: ~U ~~ ~ UJ
S .H:J: III III .. UI><O n. .
~....j > i::i > .... "'H ....'" Z Cl 0
Z 'tl - i: t.. t;" p(9 2 ~
r..~"" 0 ::l 'tl ~ 0 f:: UJ~ ~ ~ c:: ~
o t>1 .... . ..: u'" w :=>
HSt)Z H :; ~ H.... '-'H ~~ ~ '"
U H '" <>: "'I-: <~ rJ
~~oS ~ 0 ~ 0 O~ '(
!:2 <>: :<'....1>< H ~< Z
o .....t; . to ~8~ ::s ~
u ..... '" 8 t; UJ
1< Z ~ :I:'" P. Z
W .., 0 H r..u U
i:l "'~ u <>: w'" Vl UJ
~ H '" :<
~ 't> .... '" w
z 0.... U H ~
I-tUZU U '"
, .
. .
,.
, .
01,,--;
I., ./
.,,,/
~
II'
..
~ ~ ~. .
.~4~''''.\
specificity tha alleged scheduling conflicts among such
subcontractors.
C. In Paragraph 21, Plaintiff fails to specify
the dates and extent of the alleged untimely
performance of the prime sitework Contractor.
D. In Paragraph 22, Plaintiff fails to specify
the places and locations of the alleged design defects
and dimensional errors.
E. In Paragraph 2J(e) Plaintiff fails (1) to
define or describe its alleged "critical path
activities", and (2) to indicate the manner in which
such activities were adversely impacted.
F. In Paragraphs 24 and 25, Plaintiff fails to
indicate with sufficient specificity the alleged
"unanticipated and unreasonable increase in Project
costs and time for completion."
G. In Paragraph 26, Plaintiff fails to indicate
(1) the alleged sequence of work which it was alleged
to have broken, and (2) the work which was performed
out of sequence.
H. In Paragraph 27, Plaintiff fails to indicate
the manner and extent to which the site Contractor
LAW O'''ICl:B
5NELOAK~R
&
BRENNEM.\N
failed to perform in a timely manner.
I. In Paragraph 40(a), Plaintiff fails to
identify with sufficient specificity its alleged
sidewalk work in the courtyard.
-2-
J. In Paragraph 40(b), Plaintiff fails to
identify the location(s) and manner in which the
functions of the prime Plumbing contractor and prime
Electrical contractor were allegedly disrupted.
K. In Paragraph 40(c), Plaintiff fails to aver
with sufficient specificity the "serious impact" which
it allegedly sustained in its schedule.
L. In Paragraph 40(d), Plaintiff fails to aver
with specificity the manner and extent to which the
Site contractor, Electrical contractor and Mechanical
contractor were not on schedule.
LAW O'''.C[B
GNCLDAKt:R
I!r
BRENNOMN
M. In Paragraph 41, Plaintiff fails to aver with
specificity (1) the alleged "unrealistic construction
schedules", (2) the "problems caused by the District,
The Ray Group and other prime contractors", (3) the
"District's unilaterally ordered milestones", (4) the
alleged "disruption to the progress of CCI's contract
work, and (5) the alleged "additional costs".
N. In Paragraph 56, Plaintiff fails to indicate
with sufficient specificity which of the enumerated
alleged actions and omissions were caused by the
District, The Ray Group and/or other prime contractors.
o. In Paragraph 58, Plaintiff failed to indicate
the dates comprising (1) the "20 weeks" in A.1, 2 and
4, (2) the "6 months" in A.3, (3) the "5 months" in
-3-
LAW O,,.CU
SNELDAKEtl
&
BRENNEMAN
A.5, 6, 7, 8, 9, 10, 11 and 12, and (3) the "140
calendar days" in B.
P. In Paragraph 58, Plaintiff failed to state
with sufficient specificity the composition of its
various alleged damages including the number of hours,
number and identity of persons performing services,
amounts actually spent for utilities, office supplies
and truck expense, overhead, snow removal and costs to
remove and replace concrete slabs.
2. Defendant requires that all of the foregoing matters be
made more specific in order that it may fully understand
Plaintiff's claims and to make appropriate response and defense.
WHEREFORE, Defendant respectfully requests your Honorable
Court to strike off Plain~iff's Complaint for failure to conform
to Pa, R.C.P. 1019(a) or, alternatively, order and direct
Plaintiff to file a more specific Complaint to properly plead the
matters raised in the foregoing objections.
PRELIMINARY OBJECTION: FAILURE TO CONFORM TO
RULE OF COURT PER PA, R.C.P. 1028/al/21
3. The specific deficiencies identified in Paragraphs 1.0
and 1.P above are incorporated herein by reference thereto.
4. The Complaint fails to comply with Pa, R.C.P. 1019(f)
in that items of special damages have not been specifically
stated.
WHEREFORE, Defendant respectfully requests your Honorable
-4-
Court to strike off Plaintiff's Complaint for failure to conform
to Pa, R.C.P. 1019(f) and enter judgment herein in favor of
Defendant and against Plaintiff.
PRELIMINARY OBJECTIONS: LEGAL INSUFFICIENCY (DEMURRERS)
PER PA, R.C.P. 1028(al (41
A. DEMAND FOR COUNSEL FEES
5. Plaintiff demands "attorneys fees" in its Complaint.
6. The Complaint fails to set forth any legally cognizable
basis for allowing attorneys fees.
WHEREFORE, Defendant respectfully requests your Honorable
Court to dismiss said Complaint and enter judgment in favor of
Defendant and against Plaintiff.
B. DEMAND FOR MONETARY DAMAGES
7. Plaintiff demands monetary damages in the amount of
$265,000.
S. Plaintiff is barred from seeking such damages pursuant
to the contract documents which Plaintiff incorporates by
reference in its Complaint.
9. Specifically, Supplementary Condition Section 8.3.3 of
Article 8 of the General Conditions of the Contract for
LAW O"ICI:II
6NELDAKER
8<
BRENNEMAN
Construction hereinafter quoted limits Plaintiff's remedy to an
extension of time and contractually excludes monetary damages:
No payment or compensation or claim for damages
shall be made to the Contractor as compensation for
damages for any delays or hindrances from any cause
whatsoever in the progress of the Work, notwithstanding
whether such delays be avoidable or unavoidable. The
-5-
Contractor's sole remedy for delays shall be an
EXTENSION OF TIME ONLY, pursuant to and only in
accordance with this Paragraph 8.3, such extension to
be a period equivalent to the time lost, by reason of
any and all of the aforesaid causes, as determined by
the Architect. In consideration for this grant of a
time extension, the Owner and the Architect shall not
be held responsible for any loss or damage or increased
costs sustained by the Contractor through any delays
caused by the Owner or Architect or any other
Contractor or on account of the aforesaid causes or any
other cause of delay. In the event the Contractor
shall choose to litigate this clause or issue and loses
said litigation, the Contractor shall reimburse the
Owner and the Architect for their reasonable attorney's
and expert witness fees and all other costs and
expenses incurred by them in the litigation.
WHEREFORE, Defendant respectfully requests your Honorable
Court to dismiss said Complaint and enter jUdgment in favor of
Defendant and against Plaintiff.
LAw Ol'I'lCC8
SNELDAKER
a
BRENNEMAN
c. LIABILITY BASED UPON DEFENDANT'S ALLEGED
RESPONSIBILITY TO COORDINATE WORK/CONTRACTORS
10. Throughout its Complaint, Plaintiff asserts that
Defendant had responsibility to coordinate work and contractors
and, having allegedly breached such responsibility, Defendant is
allegedly liable to District for Plaintiff's alleged losses.
11. The contract documents incorporated by reference in the
Complaint place responsibility of coordination on the
contractors, specifically Plaintiff in context of this case, and
not Defendant. Therefore, Plaintiff's Complaint fails to state a
cause of action on which the relief sought can be granted when
based upon Defendant's non-existent responsibility.
WHEREFORE, Defendant respectfully requests your Honorable
-6-
CERTIFICATE OF SERVICE
I hereby certify that I am this date serving a true and
correct copy of Defendant's Preliminary Objections to Plaintiff's
Complaint by sending the same by United States first-class mail
postage paid to the Plaintiff's attorneys addressed as follows:
C. Grainger Bowman, Esquire
David W. Francis, Esquire
Michael W. Winfield, Esquire
Powell, Trachtman, Logan,
CarrIe & Bowman, P.C.
114 North Second street
Harrisburg, PA 17101
~
chard c. Snelbaker
LBAKER & BRENNEMAN, P.C.
Attorneys for Defendant
Dated: February ttA
, 1996
.'
"
;~:~.-
I"~
~'-.:'
vi"
r
~;
~:,~"
.~~.",
....-...
t
"',"
~r
?- ;
:.:~~-
~i_ .I!!!!!..
..
"'....
I
I '-, ~
, ..
I':'
-"
l.,JI'
('
L!'
.~I'
L~ -
i
':'J
,
. ~
- . ,
1.... _ .
~:.,. .-
.
. ~. ". - .. . -
..,-..., .... - - - ~,~
.,<-,.
'-',
~..-
,',
<.',f
I
I:.
I'
I
, 1
,.
, ,
".J
,,'
(.j
'>'
~
" - -
III
~< ~ ,n
0..... ~
z
"'< -:
~~ ..... ... f:2 ~ w~ ~ ~
. ..... c: -<: Zs ~
"'''' ~ ... ,..., '" z .....
zffi ... 0 "" ~o::i Zg :s ~ ~
c: 0 c:
o ei ~ .... p: '" ..e, ~8 ~ ~
p. '" U ..... g ~. ;;
d . ..:stl 0 ..... '" '" "'0 ~ ~
U '" . A p.::?;u ~~ p~
~~::lj~ Ul !:.1 0..0
Z > .....'" '/. ~ 0 0
0 ,..., '" .. . ll!o rt.
o ::>I~ ..... ~ . U ~ w6 0 ~ r>! .
0..... f-< ::>
..U UZA U ~~..... ~~ ~ ~ '"
~5iJoS,..., ~ sa . ~o~ Q
0~"'l:J< f-< [:'i ..... ~< ~
u ... ..... '" a~
I-<:~ z ~ ~ w
~ '" .. 0 Z u
is "',..., U ~~ A V) '"
~ .~~ ..... -
...
Z 0..... U
H ZU..-, U UA
.
, ,
:>- _"l" .
0' .-
-~ tr; ....
,..~ - ~.
lUr:: "
- :;1;
~(. -
',. ... ....
~r ~ ..)~~
.;:0-
.'.;i
f' ,.... .'I~
J. tl. I 1";:'-
L;;;P' C: ';;6
,:!. n.. jjt
I" "" ,..f.l..
,.... '"
u --)
0, u