HomeMy WebLinkAbout2009-6772 Civil
BLACK LANDSCAPE : IN THE COURT OF COMMON PLEAS OF
CONTRACTING, INC., : CUMBERLAND COUNTY, PENNSYLVANIA
PLAINTIFF :
V. :
:
LOBAR ASSOCIATES, INC., :
DEFENDANT : 09-6772 CIVIL TERM
BEFORE OLER, J., GUIDO, J., AND MASLAND, J.
OPINION AND ORDER OF COURT
Masland, J., June 25, 2010:--
Before the court is defendant Lobar Associates Inc.’s (Contractor)
preliminary objection to the complaint filed against it by plaintiff, Black
Landscaping Contracting, Inc. (Subcontractor) seeking payment due for
landscaping services. Contractor objects to the complaint on the grounds that
the parties are contractually obligated to resolve all disputes via arbitration.
Subcontractor argues no arbitration agreement exists between the parties.
Following argument en banc, we sustain Contractor’s preliminary objection and
dismiss Subcontractor's complaint.
I. Background
th
On July 9, 2007, Contractor entered an agreement with Harrisburg Foot
and Ankle Center (Owner) for the construction of a commercial property in
Dauphin County. The relationship between Contractor and Owner was governed
by a contract (prime contract) that included a provision requiring the parties to
09-6772 CIVIL TERM
1
resolve disputes by arbitration rather than traditional litigation. Subcontractor
was not a signatory to the prime contract.
Subsequently, Contractor entered into an agreement (subcontract) with
Subcontractor for the completion of landscaping associated with Owner's
construction project. The subcontract does not contain an express arbitration
provision. However, the subcontract does include an incorporation provision that
is the subject of the instant litigation.
Contractor argues the incorporation provision in the subcontract binds
Subcontractor to all terms of the prime contract, including the arbitration
provision. In response, Subcontractor contends the incorporation provision is
ambiguous and therefore does not bind it to the arbitration provision in the prime
contract. Specifically, Subcontractor argues “unless the subcontract
unmistakably incorporates the arbitration provision of the general contract … the
provisions at issue cannot be reasonably construed as binding [Subcontractor] to
a prior agreement to arbitrate its claims.” Pl.'s Br. at 4 (footnote omitted).
Following briefing by the parties and argument en banc, we reach the
following conclusions: (1) arbitration provisions may be incorporated by
reference through general incorporation provisions; (2) the subcontract's
incorporation provision is unambiguous; and (3) the instant dispute is within the
1
See Def.'s Ex. 2. “If Arbitration is selected by the parties as the method of
binding dispute resolution, then any claim, dispute or other matter in question
arising out of or related to this Agreement shall be subject to arbitration ….”
Prime Contract, § A.6.3.1 (emphasis added).
-2-
09-6772 CIVIL TERM
scope of the arbitration provision. Accordingly, we sustain Contractor's
preliminary objection and dismiss Subcontractor's complaint.
II. Existence of Agreement to Arbitrate
A. General Principles
At the outset we note our courts “strongly favor the settlement of disputes
by arbitration.” Langston v. National Media Corp., 596 A.2d 860, 864 (Pa. Super.
1991). Where the parties’ agreement to arbitrate is sufficiently clear, we make all
reasonable efforts to favor such agreements. DiLucente Corp. v. Pennsylvania
Roofing Co., Inc., 655 A.2d 1035, 1038 (Pa. Super. 1995). If a valid arbitration
agreement exists between the parties, and the dispute is within the scope of the
agreement, then the parties must submit to arbitration. Messa v. State Farm Ins.
Co., 641 A.2d 1167, 1170 (Pa. Super. 1994). However, if a party can establish
that it did not agree to arbitrate disputes it may be entitled to enjoin arbitration.
Smith v. Cumberland Group, Ltd., 687 A.2d 1167, 1171 (Pa. Super. 1997).
When a party to an agreement seeks to avoid proceeding to arbitration,
we must determine whether a valid agreement to arbitrate exists between the
parties and, if so, whether the dispute involved is within the scope of the
arbitration provision. Midomo Co., Inc. v. Presbyterian Housing Development
Co., 739 A.2d 180, 186-87 (Pa. Super. 1999). “[A]rbitration is a matter of
contract and, as such, it is for the court to determine whether an express
agreement between the parties to arbitrate exists.” Id. at 187.
-3-
09-6772 CIVIL TERM
Here, it is undisputed Subcontractor was not a signatory to the prime
contract between Contractor and Owner. As such, no express agreement to
arbitrate exists between Contractor and Subcontractor. Nonetheless, Contractor
asserts Subcontractor is bound by the arbitration provision in the prime contract
by the incorporation provision in the subcontract. We agree.
B. Incorporation by Reference
“As a matter of contract law, incorporation by reference is generally
effective to accomplish its intended purpose where ... the provision to which
reference is made has a reasonably clear and ascertainable meaning." Bernotas
v. Super Fresh Food Mkts., Inc., 816 A.2d 225, 231 (2002) (internal quotation
marks omitted), rev'd on other grounds, 581 Pa. 12, 863 A.2d 478 (2004). In
dicta, our courts have recognized incorporation by reference provisions in the
context of arbitration. Integrated Project Servs. v. HMS Interiors, Inc., 931 A.2d
724, 734-36 (Pa. Super. 2007). However, Pennsylvania state courts have not
squarely addressed the issue now before us. Restated for clarity, we now
address whether, and under what circumstances, a third-party nonsignatory may
be bound to an arbitration agreement on a theory of incorporation by reference.
In Bernotas, our Supreme Court held a general incorporation clause will
not incorporate indemnification provisions absent express and specific contract
language to that effect because of the longstanding policy to construe
indemnification provisions narrowly. Bernotas, 863 A.2d at 484. Subcontractor
urges us to apply a similarly strict standard where, as here, we must determine
-4-
09-6772 CIVIL TERM
whether a subcontract's incorporation provision encompasses an arbitration
provision. For the following reasons, we decline to do so.
As previously stated, Pennsylvania state courts have yet to speak directly
to the question now before us; however, the United States Court of Appeals for
the Third Circuit recently addressed this issue in a comprehensive and well-
reasoned opinion, the reasoning of which we now adopt. See Century Indem.
Co. v. Certain Underwriters at Lloyd's, London, 584 F.3d 513 (3d Cir. Pa. 2009)
(interpreting substantive Pennsylvania law). Relevant here, the Third Circuit
concluded there was no reason to apply the narrow interpretation associated with
an indemnification agreement to the interpretation of an arbitration clause,
“because such a clause is quite different from an indemnification clause.” Id. at
534. As our Supreme Court stated, indemnification provisions “impose[] an
‘unusual’ and ‘extraordinary’ obligation ….” Bernotas, 581 Pa. at 21, 863 A.2d at
483. Arbitration agreements present no similar difficulties. On the contrary,
“[p]ublic policy favors arbitration to settle disputes quickly, fairly, and
economically.” Smay v. E.R. Stuebner, Inc., 864 A.2d 1266, 1272 (Pa. Super.
2004). For these reasons, we agree with the Third Circuit and conclude “under
Pennsylvania law, arbitration provisions, like other contractual provisions, may be
incorporated by reference through general incorporation provisions.” Century
Indem. Co., 584 F.3d at 534.
-5-
09-6772 CIVIL TERM
C. Sufficiency of Subcontract's Incorporation Provision
Based on the foregoing principles, we now turn to the incorporation
provision itself. Subcontractor argues the incorporation provision is fatally
ambiguous and in support proffers an alternative interpretation of the provision in
which Subcontractor is not bound to the arbitration agreement in the prime
contract. Specifically, Subcontractor argues the provision only incorporates
prime contract documents for the “agreed purpose of [Subcontractor's] furnishing
of all materials and performance of all work … in accordance therewith.” Pl.'s Br.
at 7. Subcontractor further notes Contractor drafted the subcontract and thus all
ambiguities must be interpreted against that party.
“A contract is ambiguous if it is reasonably susceptible of different
constructions and capable of being understood in more than one sense.”
Insurance Adjustment Bureau v. Allstate, 588 Pa. 470, 481, 905 A.2d 462, 468-
69 (2006). Notably, “[t]he 'reasonably' qualifier is important: there is no ambiguity
if one of the two proffered meanings is unreasonable.” Trizechahn Gateway LLC
v. Titus, 601 Pa. 637, 652-653, 976 A.2d 474, 483 (Pa. 2009). We will not
“distort the meaning of the language or resort to a strained contrivance in order to
find an ambiguity.” Madison Constr. Co. v. Harleysville Mut. Ins. Co., 557 Pa.
595, 606, 735 A.2d 100, 106 (1999). Further, “[a]ll parts of the contract should
be interpreted together, with the goal of giving effect to each of its provisions.”
Midomo, 739 A.2d at 191.
-6-
09-6772 CIVIL TERM
Here, we conclude the incorporation provision, though inartfully drafted, is
unambiguous. It reads, in relevant part:
ARTICLE I. The [S]ubcontractor agrees to furnish all
material and perform all work as described in article ii
hereof for:
Hsbrg Foot&Ankl Grossmn
PA
For LOBAR ASSOCIATES, INC. in accordance with
this agreement, the agreement between the owner &
contractor, & in accordance with the general
conditions of the contract, supplementary conditions,
the drawings, specifications, amendments, and/or
addenda prepared by __, hereinafter called the
architect or owner's authorized agent, all of which
documents, signed by the parties thereto or identified
by the architect or owner’s authorized agent, form a
part of a contract between the contractor and the
owner dated 8/3/2007 & hereby become a part of this
contract & herein referred to as the contract
documents, & shall be available to the subcontractor
upon his request prior to and anytime subsequent to
signing this subcontract.
Def.’s Ex. 1 (emphasis added) (errors in original). The incorporation provision is
riddled with spelling errors and identifies the prime contract by an erroneous
date. However, it identified the parties to the prime contract by name and
broadly stated all documents forming a part of the prime contract “hereby
become a part of this contract ….” Def.'s Ex. 1. Further, the final line of the
provision notified Subcontractor of the existence of external contract documents
and empowered it to request those documents prior to signing the subcontract.
-7-
09-6772 CIVIL TERM
Based on our reading of the incorporation provision, we reject
Subcontractor's proffered interpretation as overly narrow and failing to effectuate
the provision as a whole. Midomo, 739 A.2d at 191. We find the only reasonable
interpretation of the incorporation provision is that it amounts to a general
incorporation of the terms of the prime contract, including the arbitration
provision, into the subcontract. Century Indem. Co., 584 F.3d at 534.
Accordingly, we conclude the incorporation provision is unambiguous and serves
to bind subcontractor to the arbitration agreement in the prime contract.
III. Scope of Arbitration Agreement
Having concluded the parties have entered an agreement to arbitrate, we
must now determine whether the instant dispute is within the scope of the
arbitration agreement. Midomo, 739 A.2d at 186-87.
We analyze arbitration agreements according to the rules of contractual
construction and adopt an interpretation giving paramount importance to the
intent of the parties and ascribe “the most reasonable, probable, and natural
conduct to the parties.” Id. at 191.
Here, we have little difficulty concluding Subcontractor's payment dispute
is within the scope of the arbitration agreement in the prime contract. Section
6.3.1. of the prime contract states “any claim, dispute or other matter in question
arising out of or related to [the prime contract] shall be subject to arbitration ….”
Def.'s Ex. 2, Prime Contract, § A.6.3.1. This provision is clearly “framed in the
broadest conceivable language” and thus encompasses the dispute between
-8-
09-6772 CIVIL TERM
contractor and subcontractor regarding payment due under the subcontract. See
Two Rivers Terminal L.P. v. Benatec Assocs. Inc., 40 Pa. D. & C. 4th 497, 502
(C.P. Dauphin 1998).
IV. Conclusion
In sum, we reach the following conclusions: (1) arbitration provisions may
be incorporated by reference through general incorporation provisions; (2) the
subcontract's incorporation provision is unambiguous; and (3) the instant dispute
is within the scope of the arbitration provision. Accordingly, we sustain
Contractor's preliminary objection and dismiss Subcontractor's complaint.
ORDER OF COURT
AND NOW, this day of June, 2010, defendant’s preliminary
IS SUSTAINEDIS DISMISSED.
objection, . Plaintiff’s complaint,
By the Court,
Albert H. Masland, J.
Gerald S. Gaetano, Esquire
For Plaintiff
Veronica J. Finkelstein, Esquire
For Defendant
:sal
-9-
BLACK LANDSCAPE : IN THE COURT OF COMMON PLEAS OF
CONTRACTING, INC., : CUMBERLAND COUNTY, PENNSYLVANIA
PLAINTIFF :
V. :
:
LOBAR ASSOCIATES, INC., :
DEFENDANT : 09-6772 CIVIL TERM
BEFORE OLER, J., GUIDO, J., AND MASLAND, J.
ORDER OF COURT
AND NOW, this day of June, 2010, defendant’s preliminary
IS SUSTAINEDIS DISMISSED.
objection, . Plaintiff’s complaint,
By the Court,
Albert H. Masland, J.
Gerald S. Gaetano, Esquire
For Plaintiff
Veronica J. Finkelstein, Esquire
For Defendant
:sal