HomeMy WebLinkAbout94-4178 CivilLIBERTY EXCAVATORS, INC., : IN THE COURT OF COMMON PLEAS OF
Plaintiff : CUMBERLAND COUNTY, PENNSYLVANIA
:
v. : CIVIL ACTION - LAW
:
LOBAR ASSOCIATES, INC., :
Defendant : NO. 94-4178 CIVIL TERM
IN RE: DEFENDANT'S PETITION FOR LEAVE OF COURT
TO JOIN FRANCIS HEISSE AS AN ADDITIONAL DEFENDANT
BEFORE HOFFER and OLER, JJ.
ORDER OF COURT
AND NOW, this ~ day of October, 1995, upon careful
consideration of Defendant's Petition for Leave of Court To Join
Francis Heisse as an Additional Defendant, as well as the briefs
and oral arguments presented in the matter, the Petition is
GRANTED.
THE Defenaant, Lobar Associates, Inc., may file a complaint
joining Francis Heisse as an additional defendant within 20 days
from the date of entry of this Order.
BY THE COURT,
John A. Gill, Esq.
75 Utley Drive
Camp Hill, PA 17011
Attorney for Plaintiff
John H. Frymyer, Jr., Esq.
2306 Columbia Avenue
Lancaster, PA 17603
Attorney for Defendant
:rc
LIBERTY EXCAVATORS, INC., : IN THE COURT OF COMMON PLEAS OF
Plaintiff : CUMBERLAND COUNTY, PENNSYLVANIA
:
v. : CIVIL ACTION - LAW
:
LOBAR ASSOCIATES, INC., :
Defendant : NO. 94-4178 CIVIL TERM
IN RE: DEFENDANT'S PETITION FOR LEAVE OF COURT
TO JOIN FRANCIS HEISSE AS AN ADDITIONAL DEFENDANT
BEFORE HOFFER and OLER, JJ.
OPINION and ORDER OF COURT
Oler, J.
This is an action for breach of contract instituted by'a
subcontractor on a project for the construction of a pool and
bathhouse for the West Shore Country Club against the general
contractor for the project. Presently before the court is
Defendant's petition for leave of court to join Francis Heisse, a
second subcontractor on the project, as an additional defendant.
STATEMENT OF FACTS
Plaintiff is Liberty Excavators, Inc., a Pennsylvania
corporation with its principal place of business situate at 1104
Fernwood Avenue, Camp Hill, Cumberland County, Pennsylvania, 17011.
Defendant is Lobar Associates, Inc., a Pennsylvania corporation,
with its principal place of business situate at 1 Old Mill Road,
Dillsburg, York County, Pennsylvania.
Plaintiff commenced this action by filing a complaint on July
26, 1994, in which it alleged that DefendaHt as general contractor
breached its agreement with Plaintiff as subcontractor by failing
to pay Plaintiff the full amount due under the agreement and by
failing to pay Plaintiff for additional work Defendant requested
NO. 94-4178 CIVIL TERM
Plaintiff to perform. On September 6, 1994, Defendant filed its
Answer with New Matter and Counterclaim to Plaintiff's Complaint in
which Defendant denied any liability to Plaintiff. On October 7,
1994, Plaintiff filed its Reply to Defendant's Answer Containing
New Matter and Counterclaim. On October 27, 1994, Defendant filed
its counter-reply to Plaintiff's new matter.
On September 27, 1994, Francis Heisse, the proposed additional
defendant in this matter, commenced a separate action in this court
against Lobar Associates, Inc., the Defendant in the instant suit,
for breach of a subcontract and unjust enrichment with regard to
the project for the construction of a pool and bathhouse for.the
West Shore Country Club.~ In .response to preliminary objections
filed by Lobar Associates, Inc., Heisse filed an amended complaint
on or about October 31, 1994.
Under the contract of Defendant Lobar Associates, Inc.t with
the owner of the West Shore Country Club, all of Defendant's work,
which included all of the proposed additional defendant's work
under the subcontract, was to be completed on or before January 1,
1994. Defendant Lobar Associates, Inc., in its Petition for Leave
of Court to join Francis Heisse as an Additional Defendant, avers
the following additional facts: As a result of the proposed
additional defendant's failure to properly ~erform its work on the
project in a good and workmanlike manner, completion of the project
~Heisse v. Lobar Associates, Inc., No. 5507 Civil Term 1994.
3
NO. 94-4178 CIVIL TERM
was delayed from January 1, 1994 to April 15, 1994. As a result of
said delay, the work of Defendant and of other subcontractors on
the project was similarly delayed.
Furthermore, Defendant avers that (1) the statement of facts
alleged in Plaintiff Liberty Excavators' complaint is sufficient to
render the proposed additional defendant alone liable, or liable
with or liable over to Defendant Lobar Associates, Inc.; (2) the
proposed joinder would not work an undue hardship upon the proposed
additional defendant nor prejudice his substantive rights, since
Heisse is currently litigating the same or similar issues in the
separate action he has commenced in this court; (3) Plaintiff
Liberty Excavators, Inc., will not be prejudiced by the proposed
joinder since Liberty Excavators, Inc., is presently an additional
defendant in the action commenced by Heisse and is already involved
in the litigation of these issues; (4) Defendant Lobar Associates,
Inc., will be severely prejudiced if not granted permission to join
Heisse as an additional defendant, since the refusal would preclude
Lobar from seeking indemnification in this action; (5) the joinder
of Heisse will not serve to delay Plaintiff's case, inasmuch as
the parties are still in the discovery stage; (6) it would be a
waste of judicial resources to require Defendant Lobar Associates,
Inc., to institute a new action to seek inde~Lnification from Heisse
if it should be found liable to Plaintiff Liberty Excavators, Inc.;
and (7) reasonable justification or excuse exists for the delay, in
4
NO. 94-4178 CIVIL TERM
that Heisse's Amended Complaint was not filed until eighty-seven
days after Plaintiff Liberty Excavators, Inc., commenced this
action, and Defendant .Lobar Associates, Inc., did not have
available all the information needed to petition the court earlier
to join Heisse as an additional defendant. This matter is
presently before the court for disposition.
STATEMENT OF LAW
Pennsylvania Rule of Civil Procedure 2253 provides the
following with regard to the time for joining an additional
defendant:
Except as provided by Rule 1041.1(e) [relating
to asbestos litigation], neither praecipe for
a writ to join an additional defendant nor a
complaint if the joinder is commenced by a
complaint, shall be' filed by the original
defendant or an additional defendant later
than sixty days after the service upon the
original defendant of the initial pleading of
the plaintiff or any amendment thereof unless
such filing is allowed by the court upon cause
shown.
Initially, it should be noted that "procedural rules
applicable to controversies involving third party procedure should
be liberally construed to avoid a multiplicity of lawsuits." Exton
Dev. v. Sun Oil Co. of Pa., 363 Pa. Super. 17, 22, 525 A.2d 402,
404 (1987).
With regard to a petition for late ~oinder, the following
principles of law are applicable where defendant does not join an
additional defendant within the sixty-day period provided for in
5
NO. 94-4178 CIVIL TERM
Pa. R.C.P. 2253: The defendant has the burden of demonstrating
sufficient cause to permit the late joinder. Lamoree v. Penn Cent.
Transp. Co., 238 Pa. Super. 380, 357 A.2d 595 (1976). "The
question of whether sufficient cause has been established so as to
permit an extension of time for the joining of an additional
defendant is a matter resting within the discretion of the trial
court. And its decision in this regard will not be disturbed
absent an abuse of discretion." Id. at 384, 357 A.2d at 596-97.
The court, in determining what is sufficient cause for an
extension of time for defendant to file a praecipe joining an
additional defendant, "should be guided by the objectives sought to
be achieved by use of the additional defendant procedure in
conjunction with the purpose for which a sixty-day limitation was
placed on its unrestricted use. In a capsule, these rules are an
attempt to provide a means to simplify and expedite the disposition
of matters involving numerous parties without subjecting the
original plaintiff to unreasonable delay in the prosecution of his
portion of the litigation." Zakian v. Liljestrand, 438 Pa. 249,
256, 264 A.2d 638, 641 (1970) (citations omitted).
With regard to the possible prejudice resulting from a late
joinder the following is instructive: "The standards which should
be applied in determining good cause ~nclude balancing the
importance of not delaying the trial of plaintiff's action against
the avoidance of multiplicity of suits. In exercising its
6
NO. 94-4178 CIVIL TERM
discretion the court must consider the length of the delay in
seeking joinder in the entire context of the case. If the
extension will prejudice any party or delay the trial of the case,
the extension should be refused." 7 Goodrich-Amram ~2253:6, at 186
(1992). "Prejudice to an additional defendant in a late joinder
does not mean the normal prejudice which always follows joinder in
a lawsuit. There must be a detriment independent of that." Id.,
at 192.
APPLICATION OF LAW TO FACT
Applying the foregoing principles of law to the facts of this
case, the court does not believe that any possible prejudice to the
proposed additional defendant is so severe as to preclude joinder
at this date. In addition, the court is of the opinion that the
joinder of Francis Heisse will save both the time and expense
generated by a multiplicity of suits and, most importantly, will
not further retard the Plaintiff's right to an expeditious
disposition of its cause. For these reasons, the following Order
will be entered:
ORDER OF COURT
AND NOW, this ~ day of October, 1995, upon careful
consideration of Defendant's Petition for Leave of Court To Join
Francis Heisse as an Additional Defendantj as well as the briefs
and oral arguments presented in the matter, the Petition is
GRANTED.
7
NO. 94-4178 CIVIL TERM
THE Defendant, Lobar Associates, Inc., may file a complaint
joining Francis Heisse as an additional defendant within 20 days
from the date of entry of this Order.
BY THE COURT,
J. Wesley Oler, . J.
John A. Gill, Esq.
75 Utley Drive
Camp Hill, PA 17011
Attorney for Plaintiff
John H. Frymyer, Jr., Esq.
2306 Columbia Avenue
Lancaster, PA 17603
Attorney for Defendant
:rc