HomeMy WebLinkAbout93-0026 CivilROGELE, INC., IN THE COURT OF COMMON PLEAS OF
Plaintiff CUMBERLAND COUNTY, PENNSYLVANIA
V. CIVIL ACTION - EQUITY
E & B ENTERPRISES, INC.,
Defendant NO. 26 EQUITY 1993
IN RE: ADJUDICATION
BEFORE OLER, J.
DECREE NISI
AND NOW, this 7t4 day of September, 1993, upon consideration of Plaintiffs
Complaint and following a nonjury trial, the Court finds in favor of Plaintiff and
against Defendant in the amount of $32,939.73, with interest at the legal rate of 6%
from February 8, 1993.
IF NO MOTION for post -trial relief is filed within 10 days, the Prothonotary
shall upon praecipe enter this decree nisi as the final decree, with judgment in the
amount indicated in favor of Plaintiff.*
BY THE COURT,
. Wesley Oler,
*See Pa. R.C.P. 227.1, 227.4
Charles W. Rubendall, II, Esq.
210 Walnut Street
P.O. Box 11963
Harrisburg, PA 17108-1963
Attorney for Plaintiff
Geoffrey V. Seay, Esq.
Robinson Building
Suite 1600
42 South 15th Street
Philadelphia, PA 19102
Attorney for Defendant
:rc
ROGELE, INC.,
Plaintiff
V.
E & B ENTERPRISES, INC.,
Defendant
Oler, J.
IN THE COURT OF COMMON PLEAS OF
CUMBERLAND COUNTY, PENNSYLVANIA
CIVIL ACTION - EQUITY
NO. 26 EQUITY 1993
IN RE: ADJUDICATION
BEFORE OLER, J.
OPINION AND DECREE NISI
This case in equity arises out of a contract between a general contractor, E &
B Enterprises, Inc. (Defendant), and a subcontractor, Rogele, Inc. (Plaintiff), for
certain work at the Navy Ships Parts Control Center in Mechanicsburg, Pennsylvania.
Plaintiff subcontractor has sued for payment of the balance of its bill for performing
the work; Defendant contractor has defended on the ground that the work was
defective, resulting in various expenses which should be deducted from its obligation
to Plaintiff.' A nonjury trial was held in this matter before the undersigned judge on
Wednesday, September 1, 1993. Based upon the evidence and stipulation of counsel
presented at the trial, the following Findings of Fact, Discussion and Decree Nisi are
made and entered:
FINDINGS OF FACT
1. Plaintiff is Rogele, Inc., a corporation specializing in construction work,
having offices at 1025 South 21st Street, Harrisburg, Dauphin County, Pennsylvania.
1 The relief initially sought by Plaintiff also included an injunction to prevent Defendant
from incurring such expenses and to permit amelioration of any defects by Plaintiff itself.
However, this aspect of the case became moot by virtue of Defendant's having completed the
corrective work.
No. 26 Equity 1993
2. Defendant is E & B Enterprises, Inc., a corporation also specializing in
construction work, having offices at 3316 Fairmount Avenue, Philadelphia,
Pennsylvania.
3. On July 28, 1992, the Officer in Charge of Naval Facilities Contracts solicited
sealed bids for certain construction work on the grounds of the Navy Ships Parts
Control Center in Mechanicsburg, Cumberland County, Pennsylvania.
4. The Project Title of this work was "Repair Storm Water Inlets, Navy Ships
Parts Control Center, Mechanicsburg, PA."
5. The General Description of the work was given as follows:
The work includes the removal of deteriorated sections of
inlets, grates and frames; install new inlet boxes with
grated top unit and install proper lengths of new
intersecting drainage pipe; disposal off Government
property of removed materials; re -construction of adjacent
items of work as shown on the contract drawings and
incidental related work.
6. The Estimated Price Range for the work was given as "[b]etween $25,000.00
and $100,000.00," and the solicitation noted that "[t]his acquisition is set-aside for
small disadvantaged business."
7. Bids were opened on August 27, 1992.
8. On September 17, 1992, Defendant E & B Enterprises, Inc., was awarded the
contract, with a bid of $72,032.00.
9. The contract was to commence on September 17, 1992, and to be completed
2
No. 26 Equity 1993
by January 29, 1993.
10. Basically, Defendant E & B Enterprises, Inc., had contracted with the
federal government to replace 38 storm water inlets at the aforesaid Mechanicsburg
naval facility.
11. Defendant purchased new inlets, which were prefabricated, or "precast,"
from an affiliate of Plaintiff Rogele, Inc.
12. On October 19, 1992, Defendant engaged Plaintiff Rogele, Inc., as a
subcontractor to install the new inlets, the plan being that Defendant would remove
the old ones.
13. Defendant commenced work on or about October 26, 1992, and eventually
succeeded in removing eight of the 38 inlets; however, it found that this operation on
its part was proceeding too slowly in view of the contract deadline.
14. Accordingly, Defendant arranged with Plaintiff Rogele, Inc., to perform the
removal of the remaining 30 inlets, at an additional price.
15. However, this arrangement appears to have been unsatisfactory to the
federal government, because it would have resulted in too small a portion of the project
being done by the "small disadvantaged business" which had been awarded the
contract.
16. Accordingly, a purchase order involving Defendant contractor and Plaintiff
subcontractor was effected on December 17, 1992, whereby Plaintiff would remove the
No. 26 Equity 1993
remaining 30 inlets, but would not be responsible for a certain portion of the project
— i.e., the removal in the spring of 1993 of a temporary winter patch in the area of
each inlet (known as a "cold patch") and installation of permanent, concrete material
in its place; this portion of the project would be Defendant's responsibility.
17. Plaintiff Rogele, Inc., largely completed its portion of the project by the end
of January, 1993 (although some additional work, such as seeding and certain
adjustments, was done by Plaintiff in May of 1993).
18. Satisfactory compaction, or density, test results were obtained by an
independent laboratory retained by Plaintiff Rogele, Inc., with respect to "fill" placed
in the area of each inlet.
19. Defendant has to date paid Plaintiff Rogele, Inc., the sum of $11,500.00 for
its work.
20. By stipulation of counsel, it is agreed that an additional sum of $38,567.88,
less any amount necessary to correct deficiencies in the work, plus interest at the rate
of six percent per annum from February 8, 1993, is due Plaintiff from Defendant.
21. This figure results from the original October 19, 1992, purchase order for
$22,800.00; the second purchase order on December 17, 1992, for $25,000.00; and
incidental charges of $2,267.88; less the $11,500.00 payment.
22. Over the winter, a certain amount of settling in the inlet areas occurred,
with the result that a number of personnel at the Navy Parts Ships Control Center
4
No. 26 Equity 1993
were alarmed and contacted the office of Michael Paquette, construction representative
and project manager at the Control Center.
23. In view of the amount of settling involved, Mr. Paquette initially suspected
that the laboratory retained by Plaintiff Rogele, Inc., to perform density testing had
falsified the data; he has since concluded otherwise.
24. Upon being informed by Mr. Paquette's office of suspected improprieties in
connection with Plaintiff's work, Defendant employed its own independent testing lab
to perform density testing at the inlets.
26. On June 14, 1993, the new lab tested the fill at two inlets and found that
neither was sufficiently compacted to meet the 95% degree of density required by the
contract specifications; one tested at 86.8% and one at 87.1%.
26. The new lab made the following note and recommendation:
The Contractor [E & B Enterprises, Inc.] compacted
existing crushed stone modified backfill at inlet #82. The
material compacted an additional 4"-6". Requested Declan
Phillips (Ambric [new lab] Engineer) for additional
recommendation. To properly achieve the compaction
requirement, all backfill material should be removed and
recompacted to assure future settlement would not occur.
Advised Contractor (E & B Enterprises, Inc.) of
recommendation and they said they would comply with
recommended procedure at several locations as a trial.
27. On June 16, 1993, the new lab tested the fill at 17 other inlets and found
the compaction levels below specifications in all cases.
28. During eight days between June 14, 1993, and June 26, 1993, from one to
5
No. 26 Equity 1993
three employees of Defendant — supervisors and laborers — worked with a
representative of the new lab and brought the compaction degrees at the inlets up to
specifications; in the process, eight sites were excavated and completely recompacted.
29. According to Defendant's records, the supervisors spent 65 hours and the
laborers spent 114 hours during those days.
30. On another day during this period, three employees of Defendant — a
supervisor and two laborers — picked up equipment in the form of a "bob cat" machine
and "tampers."
31. According to Defendant's records, the supervisor spent 6 hours and the
laborers spent 12 hours on that day.
hour.
32. Defendant pays its laborers $18.10 per hour and its supervisors $27.15 per
33. At those rates, Defendant incurred expenses for the aforesaid eight days for
supervisors and laborers of $3,828.15, and expenses for the aforesaid one day of
equipment pickup for a supervisor and laborers of $380.10.
34. Defendant was charged $1,700-00 by the new lab.
35. Defendant also claims additional expenses for hotel accommodations for its
employees and for equipment rental, but these have not been substantiated.
36. Defendant has recently submitted a backcharge to Plaintiff for the allegedly
defective work in the amount of $13,759.26.
n
No. 26 Equity 1993
37. Plaintiff's president testified that in his opinion a fair price for excavation
and recompaction in the area of a given inlet requiring such treatment would be about
$130.00, including testing fees.
38. Plaintiff also complains that it was not given an opportunity by Defendant
to repair any deficiencies in the work itself.
39. In view of the initial suspicion on the part of the government project
manager of improprieties in connection with compaction of fill at the inlets, the Court
finds that the decision of Defendant to employ a second testing lab and not to utilize
Plaintiff to bring compaction levels up to specifications was not unreasonable.
40. The $1,700.00 bill of the new lab, which is an expense incurred by
Defendant in attempting to deal with governmental complaints about the work done
by Plaintiff, is found to be reasonable under the circumstances and fairly chargeable
to Plaintiff.
41. The fair and reasonable cost for bringing the inlet fill areas up to
specifications is found to have been $3,928.15.
DISCUSSION
In the present case, the Court believes that some remedial work was necessary
with respect to Plaintiff's performance on its subcontract with Defendant. On the
other hand, it also appears that the initial reaction of the government may have
exaggerated the seriousness of the deficiencies, precipitating an immediate, and less
7
No. 26 Equity 1993
than completely efficient, response on the part of Defendant. Although the Court has
found that the Defendant's refusal to rely upon Plaintiff to correct the deficiencies was
defensible,' only a fair and reasonable amount for correction of the work can be
backcharged. This amount, in the Court's view, has not been shown to exceed
$5,628.15, including testing fees.
DECREE NISI
AND NOW, this `day of September, 1993, upon consideration of Plaintiff's
Complaint and following a nonjury trial, the Court finds in favor of Plaintiff and
against Defendant in the amount of $32,939.73, with interest at the legal rate of 6%
from February 8, 1993.
IF NO MOTION for post -trial relief is filed within 10 days, the Prothonotary
shall upon praecipe enter this decree nisi as the final decree, with judgment in the
amount indicated in favor of Plaintiff.*
BY THE COURT,
J. W6 -ley Oler, Jr. J.
*See Pa. R.C.P. 227.1, 227.4
' See generally Johnson v. Fenestra, Inc., 305 F.2d 179 (3d Cir. 1962).
N.
No. 26 Equity 1993
Charles W. Rubendall, II, Esq.
210 Walnut Street
P.O. Box 11963
Harrisburg, PA 17108-1963
Attorney for Plaintiff
Geoffrey V. Seay, Esq.
Robinson Building
Suite 1600
42 South 15th Street
Philadelphia, PA 19102
Attorney for Defendant
:rc
m